The General Contractor's Guide: Bid to Closeout
By Wyatt Cooper · Published · 8 min read
Key takeaways
- A general contractor is responsible for delivering the whole work under its contract: pricing it, buying it out, building it to the documents and schedule, paying its subs, and handing over a finished building with its paper.
- Each phase hands the next one its inputs: the bid becomes the budget, buyout becomes the commitments, and the subcontracts set how changes, billing and closeout run.
- Most of a GC's risk is in the gaps between parties, so the job runs on records: RFIs, submittals, daily logs, change orders and pay apps, each with an owner and a date.
- Closeout starts at buyout: the punch list and the closeout documents are what stand between substantial completion and final payment.
A general contractor's responsibilities run from bid to closeout: price the work and win it, buy it out with subcontracts that match the scope, plan submittals and the schedule, run the field (RFIs, daily logs, inspections, quality), manage changes and the budget, bill the owner and pay the subs, then close the job with a punch list, a closeout package and warranties. This guide walks each phase and links the detailed how-tos.
What a general contractor is responsible for
Under a typical design-bid-build or negotiated contract, the GC contracts with the owner to deliver the whole work shown in the contract documents, for a price and by a date. It does not do every trade itself: it hires subcontractors and suppliers, coordinates them, and stays responsible to the owner for their work. The architect and engineers design the building and, during construction, administer the contract for the owner; the GC builds it.
That responsibility includes quality. On federal construction, the contractor must "maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements", and replace or correct nonconforming work without charge (FAR 52.246-12). Private contracts say it differently, but the idea is the same: the GC answers for the work, its own and its subs'.
The sections below follow the job in order. Each names the GC's work in that phase and links the guides that go deeper. For the whole job from every party's seat, see the construction project lifecycle.
Bidding: price the work and win it
Bidding turns a set of drawings into a number you can stand behind. Break the scope into trade packages, invite enough qualified subs to each to get real competition, answer their questions in writing, and issue addenda to everyone at once. When the bids come in, compare them on the same scope, not just the price.
- Write each trade's scope so a sub can bid it without guessing: the spec sections, the drawings, what is in and what is by others.
- Level every trade before you carry a number: how to level subcontractor bids adds back missing scope and prices the exclusions so the lowest leveled bid, not the lowest number, wins.
- Carry your own estimate for general conditions, self-performed work, fee and contingency.
- Price the owner's alternates separately, as the bid form asks.
In Conflo: trade bids, bid leveling, the estimate and the proposal.
Buyout and preconstruction: contracts, submittals and the schedule
Once you win, buy the job out: award each trade and sign a subcontract whose scope exhibit matches the leveled bid, including the exclusions you accepted. Buyout is where the budget becomes commitments, and where the gap between the two is your buyout savings or loss.
- Put the owner contract's terms that matter into each subcontract: retainage, pay terms, change notice, insurance, warranty and closeout obligations.
- Write the closeout list into each subcontract now, from the closeout article of every spec section in its scope.
- Build the submittal register from the specs and set the order: long-lead items first.
- Collect each sub's insurance certificates and compliance documents before it mobilizes.
- Build the schedule with the subs who will work to it, and agree each one's schedule of values.
In Conflo: buyout, commitments, submittals, compliance and the schedule.
Construction: run the field on records
In the field, the GC's job is coordination: the right trade in the right place with the right information, materials and inspections. Most disputes start in a gap between two parties, so put every question, answer and instruction on a record with a name and a date.
- RFIs: one question each, with the sheet, the spec section, a proposed answer and a due date. See how to write an RFI.
- Submittals: review them against the specs before they go to the architect, and do not let anything be bought or built before it is approved.
- Daily logs: crews, work done, deliveries, weather, delays and visitors, every day.
- Inspections: schedule them ahead, and log the results and the corrections.
- Quality: punch each area as it finishes, not just at the end.
In Conflo: RFIs, submittals, daily logs, inspections and meetings.
Money: changes, the budget, pay apps and paying subs
The money side runs alongside the field. Every change has a reason, a price and a schedule effect; every month the owner is billed for the work in place and the subs are paid from it. Keep the budget current so you see a loss while there is still time to act on it.
- Change orders: price them from the subs' quotes and your own costs, apply the markups your contract allows, and get them approved before the work where you can. See how to price a change order.
- Pay apps: collect the subs' pay applications, review each against the work in place, roll them into the owner pay app, and calculate retainage correctly.
- Lien waivers: collect them from subs and suppliers with each payment, conditional for this payment and unconditional for the last.
- Budget: track original budget, approved changes, commitments and costs to date against the projected final cost.
Paying subs on time is a legal duty as well as a relationship. On federal fixed-price construction, each payment request certifies that subs and suppliers have been paid from earlier payments and will be paid on time from this one (FAR 52.232-5), and subcontracts must require payment within 7 days after the prime is paid, with interest if late and written notice of any withholding (FAR 52.232-27). States have their own prompt payment laws; check yours. The sub's side of billing is in how a subcontractor fills out a pay application.
In Conflo: change orders, budget, commitments and pay applications.
Closeout: punch list, substantial completion and the package
Closeout is where jobs lose months. Punch each area as its finishes go in, so that when you ask for the substantial completion inspection your own list is nearly closed. See how to build a punch list, or start from the free punch list template.
Substantial completion is the date the owner can use the work for its intended purpose; on AIA documents, A201-2017 Section 9.8.1 defines it that way (AIA Contract Documents). On AIA-based contracts the contractor prepares the list of items to complete or correct, the architect verifies and amends it, and the certificate sets the time to finish them and who takes on maintenance, utilities and insurance; warranties start that day unless it says otherwise (AIA's G704 summary). How the architect decides is in how an architect decides substantial completion.
Then assemble and deliver the closeout package: record drawings, O&M manuals, warranties, attic stock, training records, test reports and final lien waivers, by spec section. See how to assemble a closeout package, and for what the owner checks, what an owner should get at closeout. Final payment usually waits for the package and the closed punch list.
In Conflo: the punch list, the closeout package and warranties.
Every guide for general contractors
Preconstruction
How Do Architects Write Construction Specifications?
How architects write construction specifications: MasterFormat numbers, the three-part section, specs versus drawings, and an example section.
· 6 min read
Bidding
How Do You Answer Bidder Questions During a Bid?
How a GC handles pre-bid questions from subs: one written channel, a question log, answers to every bidder, and when an answer must become an addendum.
· 7 min read
Money
How Do You Back-Charge a Subcontractor?
How a GC back-charges a subcontractor: the contract basis, notice and a chance to cure, a cost record by day, the markup, and the deduction the sub signs.
· 6 min read
Money
How Do You Bill a Change Order on a Pay App?
Add an executed change order to your pay app: its own line, the new contract sum, partial billing, deducts and retainage, with a worked example.
· 7 min read
Money
How Do You Bill for Stored Materials on a Pay App?
Bill delivered but uninstalled materials: the backup owners ask for, on site vs off site, and how stored amounts move to installed work. Worked example.
· 7 min read
Money
How Do You Bill Time-and-Materials Work?
Bill T&M work a GC will pay: written direction first, a ticket signed every day, labor, equipment and materials at agreed rates, markup once. Example.
· 7 min read
Preconstruction
How Do You Build a Construction Schedule?
Build a commercial construction schedule step by step: activities from the estimate, durations from crew rates, logic, procurement and the critical path.
· 8 min read
Bidding
How Do You Calculate Concrete for a Slab?
How to calculate cubic yards of concrete for a slab, footings and piers: the formulas, a worked example, and how much extra to order and why.
· 6 min read
Bidding
How Do You Calculate Labor Burden for a Crew?
Calculate labor burden for a crew: payroll taxes, workers' comp, insurance and benefits over wages, then the cost per productive hour to bid with.
· 6 min read
Closeout
How Do You Close Out a Subcontract?
A GC's checklist to close out a subcontract: settle the last change orders, take the final pay app, release retainage against waivers, record the warranty.
· 6 min read
Closeout
How Do You Collect O&M Manuals From Subcontractors?
How a GC collects O&M manuals from every trade: request them early by spec section, check them against what was installed, and send back the thin ones.
· 6 min read
Bidding
How Do You Decide Whether to Bid a Job?
A go/no-go method for general contractors: the factors to score before estimating, how to weight them, and a worked score for a fictional clinic.
· 8 min read
Construction
How Do You Do a Job Hazard Analysis?
Do a job hazard analysis as OSHA 3071 lays it out: break the task into steps, name each hazard, set controls in order, with a worked saw-cutting JHA.
· 6 min read
Bidding
How Do You Do a Quantity Takeoff?
How a subcontractor does a quantity takeoff: scope from the specs, written dimensions, units, waste, a sheet reference on every line and a check.
· 7 min read
Construction
How Do You Document a Weather Delay?
How a GC documents a weather delay that wins a time extension: the daily log entry, the critical path, comparing to normal weather, and the notice.
· 8 min read
Money
How Do You Fill Out Certified Payroll (WH-347)?
Fill out weekly certified payroll on Form WH-347: the header, each worker's hours, rates, fringes and deductions, and the Statement of Compliance.
· 9 min read
Construction
How Do You Fill Out the OSHA 300 Log?
Fill out the OSHA 300 log from 29 CFR 1904: who keeps one, which construction injuries are recordable, columns A to M, and a worked year with 300A totals.
· 8 min read
Money
How Do You Forecast Cost to Complete on a Job?
Forecast cost to complete line by line: remaining commitments, self-performed work at its real production rate, and time-based costs against the schedule.
· 6 min read
Closeout
How Do You Get a Certificate of Occupancy?
The GC's sequence for a certificate of occupancy: plan the final inspections early, clear life safety first, and know when a temporary certificate helps.
· 6 min read
Preconstruction
How Do You Get Added as Additional Insured?
How a GC gets added as additional insured on a sub's policy: the subcontract wording, the endorsement to ask for, and why a certificate alone isn't enough.
· 6 min read
Money
How Do You Issue a Subcontract Change Order?
Issue a subcontract change order the sub can sign and bill: what goes on it, the revised subcontract sum, time, and the reservation of claims. Example.
· 8 min read
Construction
How Do You Keep an RFI Log?
How a GC keeps an RFI log: the columns that matter, ball in court and days open, a filled-in log, and how to run it at the weekly meeting.
· 7 min read
Money
How Do You Make a Miller Act Payment Bond Claim?
A Miller Act payment bond claim, step by step: who can claim, the 90-day notice, the one-year suit deadline from 40 U.S.C. § 3133, with dated timeline.
· 8 min read
Bidding
How Do You Prequalify a Subcontractor?
How a GC prequalifies a subcontractor before inviting it to bid: the questionnaire, the checks, a dollar limit per job, and a worked example.
· 7 min read
Bidding
How Do You Price a Bid Alternate?
Price add and deduct bid alternates: each trade's alternate price, your own work, the base bid's markups, and what each one includes.
· 6 min read
Bidding
How Do You Price General Conditions?
Price general conditions from the schedule: staff by the weeks on site, facilities by the month, fixed items as lump sums, and a weekly delay rate.
· 7 min read
Preconstruction
How Do You Read a Certificate of Insurance (ACORD 25)?
How to read an ACORD 25 certificate of liability insurance box by box, and what a GC checks in each one against the subcontract's insurance exhibit.
· 7 min read
Bidding
How Do You Read Construction Drawings Before You Bid?
How a subcontractor reads a drawing set before bidding: the index and notes, your sheets and everyone else's, details, schedules, specs and gaps.
· 7 min read
Preconstruction
How Do You Run a Preconstruction Kickoff Meeting?
How a GC runs the preconstruction meeting: who attends, a worked agenda of procedures to agree before work starts, and what to record.
· 7 min read
Construction
How Do You Run a Toolbox Talk?
Run a toolbox talk in ten minutes: one hazard from today's work, shown at the work, the controls, the crew's questions, and a record of who attended.
· 6 min read
Construction
How Do You Run an OAC Meeting?
How a GC runs an owner-architect-contractor meeting: who attends, what each party brings, a worked agenda, and how open items carry to the next one.
· 8 min read
Preconstruction
How Do You Set Up Cost Codes for a Construction Job?
Set up construction cost codes from CSI MasterFormat: pick the detail, match codes to bid packages, and use them from estimate to pay app.
· 7 min read
Bidding
How Do You Spot a Sub Bid That Is Too Low?
How a GC tells a sub bid that is too low from a good price: the checks after leveling, a worked plumbing example, and how to ask the bidder to verify.
· 8 min read
Money
How Do You Track a Budget Against Commitments?
Track a construction budget against committed cost by cost code: revised budget, signed commitments, buyout variance and exposure, with a worked table.
· 7 min read
Preconstruction
How Do You Track Long-Lead Items on a Job?
How a GC tracks long-lead items: work back from the need-on-site date through lead time and submittal review to an order-by date, and review it weekly.
· 6 min read
Preconstruction
How Do You Track Subcontractor COIs and Expirations?
A GC's method for tracking subcontractor certificates of insurance: one log per job, what to record, a 30-day renewal window, and when to hold payment.
· 6 min read
Construction
How Do You Update a Construction Schedule?
How to update a construction schedule each month: the data date, actual dates, remaining durations, the baseline comparison and a slip narrative.
· 7 min read
Money
How Do You Use Earned Value on a Construction Job?
Earned value on a construction job, worked on one trade: planned value, earned value, actual cost, CPI, SPI and estimate at completion.
· 6 min read
Bidding
How Do You Write a Bid Addendum?
How a GC writes a bid addendum to trade bidders: what goes in it, how to word each change, when to send it, and how to collect acknowledgments.
· 8 min read
Construction
How Do You Write a Construction Incident Report?
Write a construction incident report: the first hour, the facts to record, the root cause, and how a filled-in report decides the OSHA 300 log.
· 7 min read
Preconstruction
How Do You Write a Purchase Order for Materials?
What a construction purchase order for materials includes: items, delivery and freight terms, submittal release, stored materials and a worked example.
· 7 min read
Construction
How Do You Write a Recovery Schedule?
How a GC writes a recovery schedule: measure the slip, price crews, overtime and resequencing, show the days each recovers, and keep the logic honest.
· 8 min read
Preconstruction
How Do You Write a Site Logistics Plan?
How a GC writes a site logistics plan: gates, deliveries, laydown, the crane, fire and exits, the OSHA minimums, and one plan per phase.
· 8 min read
Preconstruction
How Do You Write a Site-Specific Safety Plan?
Write a site-specific safety plan from OSHA's own construction rules: the emergency page, hazards by phase, who controls each one, and a filled-in example.
· 7 min read
Construction
How Do You Write a Weekly Owner Update?
How a GC writes a one-page weekly owner update: the numbers owners read, schedule status in one line, decisions needed, and an example.
· 7 min read
Money
How Does a Florida Notice to Owner Work?
Florida's notice to owner from Fla. Stat. § 713.06: who serves it, the 45-day deadline, the 40-day mailing rule, the required warning and a dated example.
· 8 min read
Money
How Does a GC Review a Sub's Change Order Request?
Review a sub's change order request like the owner will: is it a change, was notice on time, do hours, prices and markup hold up. Worked example.
· 8 min read
Closeout
How Does a Sub Close Out Punch List Items?
A subcontractor's method for punch lists: sort your items by area, fix them in one trip, prove each fix with a photo, and get them closed the first time.
· 6 min read
Closeout
How Does a Subcontractor Keep As-Built Drawings?
How a subcontractor keeps as-built drawings: one marked-up set, red, green and blue, updated weekly, buried work dimensioned, turned in on time.
· 6 min read
Closeout
How Does a Subcontractor Submit a Final Pay App?
A sub's final pay app: bill every line to 100%, reconcile change orders, list open claims, and send the closeout papers and final waivers. Worked example.
· 8 min read
Construction
How Does a Subcontractor Write a Notice of Delay?
How a subcontractor writes a notice of delay to the GC: what to include, when to send it, a sample letter, and why the subcontract's deadline comes first.
· 7 min read
Preconstruction
How Does a Waiver of Consequential Damages Work?
What an owner gives up and gets under a mutual waiver of consequential damages, how liquidated damages fit, and what to ask before you sign it.
· 6 min read
Construction
How Does an Architect Issue a Drawing Revision?
How an architect issues a revised drawing sheet: clouds around what changed, a delta with the revision number, the revision block and the issue.
· 7 min read
Construction
How Does an Architect Write a Field Report?
How an architect writes a site visit field report: what to record, the words to use and avoid, a filled-in example, and carrying open items.
· 7 min read
Money
How Does California's 20-Day Preliminary Notice Work?
California's preliminary notice from the Civil Code: who sends it, to whom, the 20-day rule, what it must say and how to serve it, with a dated example.
· 8 min read
Closeout
How Does Termination for Convenience Work?
What a termination for convenience clause lets an owner or GC do, what a sub must do on notice, and what it can recover, with a worked settlement.
· 6 min read
Bidding
How Earthwork Subs Bid and Bill Commercial Work
How an earthwork and site utility sub bids and bills commercial work: scope splits, unit prices for rock and bad soil, haul math, trench costs, a pay app.
· 8 min read
Preconstruction
How Much Insurance Does a Subcontractor Need?
The coverages a subcontract asks for, how a GC sets the limits, and how to check your policies against the insurance exhibit before you sign.
· 7 min read
Bidding
How Much Overhead and Profit Should a GC Carry?
Work out a GC's overhead and profit from its own books: home-office overhead over annual volume, plus target profit, turned into the markup a bid needs.
· 6 min read
Construction
How Should a Contractor Prepare for an OSHA Inspection?
Prepare for an OSHA inspection on a construction site: the records to have ready, who meets the inspector, and each step of the visit from OSHA's manual.
· 6 min read
Construction
How Should an Owner Respond to a GC's Delay Claim?
An owner's first 30 days after a contractor's delay claim: check the notice, sort the days by cause, test the schedule and money, answer in writing.
· 6 min read
Closeout
How Should an Owner Track Building Warranties?
An owner's method for tracking building warranties: one list with start dates and terms, expirations worked out, and walks before the clock runs out.
· 6 min read
Construction
How to Write Construction Meeting Minutes (With Example)
How to write construction meeting minutes: header, attendance, numbered old and new business, action items with owners and dates, and an example.
· 7 min read
Definition
Lump Sum vs Cost-Plus: What Is the Difference?
A lump-sum contract fixes the price; a cost-plus contract pays actual cost plus a fee. Definitions, a worked comparison, and where a GMP fits.
· 3 min read
Preconstruction
OCIP vs CCIP: How Does Wrap-Up Insurance Work?
OCIP vs CCIP for owners: who buys a wrap-up, what it covers, how bids change, where the gaps are, and how to tell whether it saves money on your project.
· 7 min read
Money
Pay-if-Paid vs Pay-When-Paid: What Do They Mean?
Pay-if-paid shifts the risk of owner nonpayment to the sub; pay-when-paid only sets timing. How to tell them apart, and three state statutes on them.
· 8 min read
Construction
Revise and Resubmit: What Should a Sub Do Next?
A submittal came back revise and resubmit. What a sub should do next: read every comment, answer each one, and get the next revision approved fast.
· 6 min read
Definition
What Are As-Built Drawings?
As-built drawings are the contract drawings marked up to show what was actually built. Definition, how they differ from record drawings, and an example.
· 3 min read
Definition
What Are Liquidated Damages in Construction?
Liquidated damages are a daily amount, fixed in the contract, that a contractor pays for finishing late. Definition, a worked example, LDs vs. penalties.
· 3 min read
Definition
What Are Means and Methods in Construction?
Means and methods are how the contractor builds the work: equipment, crews, sequence and safety. Definition, who is responsible, and an example.
· 3 min read
Definition
What Are Performance and Payment Bonds?
A performance bond guarantees the work gets finished; a payment bond, that subs and suppliers get paid. Definitions, the Miller Act rule, an example.
· 3 min read
Definition
What Are Stored Materials on a Pay App?
Stored materials are delivered but not yet installed, billed in their own pay app column. Definition, the rules for on-site and off-site, and an example.
· 4 min read
Definition
What Are the Contract Documents in Construction?
The contract documents are the agreement, conditions, drawings, specifications, addenda and modifications that together make up a construction contract.
· 3 min read
Construction
What Do You Do After a Failed Building Inspection?
What a GC does after a failed building inspection: split the correction notice by trade, fix and check, book the reinspection, protect the schedule.
· 7 min read
Definition
What Does Additional Insured Mean?
An additional insured is a company added to someone else's liability policy by endorsement. What it means on a job, and why a certificate isn't enough.
· 3 min read
Construction
What Does OSHA Require for Fall Protection?
OSHA fall protection in construction from 29 CFR 1926.501: the 6-foot rule, where other heights apply, the fall protection plan exception, a roof example.
· 8 min read
Construction
What Does OSHA Require for Trench Safety?
OSHA trench rules from Subpart P: the 5-foot rule and its exceptions, soil types, sloping, shoring and trench boxes, daily inspections, a worked trench.
· 8 min read
Construction
What Does OSHA's Silica Rule Require on a Job?
OSHA's construction silica rule, 29 CFR 1926.1153, task by task: Table 1 controls and respirators, the four-hour rule, the written plan, a worked day.
· 8 min read
Definition
What Is a Back-Charge in Construction?
A back-charge is a deduction from a sub's payment for costs the GC incurred because of the sub's work. Definition, a worked example, and how it differs.
· 3 min read
Definition
What Is a Bid Alternate?
A bid alternate is a separately priced add or deduct option the owner may accept. Definition, a worked example, and alternate vs. allowance.
· 3 min read
Definition
What Is a Bid Bond?
A bid bond guarantees a bidder will sign the contract and furnish bonds if it wins. Definition, a federal example, and bid bond vs. performance bond.
· 3 min read
Definition
What Is a Bid Form in Construction?
A bid form is the document a bidder fills in and signs to submit its price. What it holds, a filled-in example, and how it differs from a proposal.
· 3 min read
Definition
What Is a Bid Package in Construction?
A bid package is the scope and documents sent out for one price, usually one trade's work. What goes in it, an example, and bid package vs. bid set.
· 3 min read
Definition
What Is a Certificate of Insurance (COI)?
A certificate of insurance summarizes the policies a contractor carries on the day it is issued. What it shows, an example, and why it isn't the policy.
· 3 min read
Definition
What Is a Certificate of Occupancy?
A certificate of occupancy is the building department's approval to occupy a building. Definition, temporary COs, and how it differs from completion.
· 3 min read
Definition
What Is a Change Order in Construction?
A change order is a signed amendment to a construction contract that changes the work and adjusts price, time or both. Definition and a worked example.
· 3 min read
Definition
What Is a Change Order Request?
A change order request is a contractor's priced proposal for a change, sent before a change order exists. Definition, an example, and the notice clock.
· 4 min read
Definition
What Is a Committed Cost in Construction?
Committed cost is the value of signed subcontracts and POs on a job, billed or not. Definition, a budget example, and how it differs from actual cost.
· 3 min read
Definition
What Is a Cost Code in Construction?
A cost code is the number that tags every budget line, contract, invoice and change order to the same category of work. Definition and an example.
· 3 min read
Definition
What Is a Daily Log in Construction?
A daily log is the superintendent's same-day record of a job site: weather, crews, work, deliveries, delays. Definition, an example, and why it matters.
· 3 min read
Definition
What Is a Letter of Intent in Construction?
A letter of intent says the work will be awarded before the contract is signed, sometimes authorizing limited work. Definition and an example.
· 3 min read
Definition
What Is a Long-Lead Item in Construction?
A long-lead item takes so long to approve, build and ship that it must be ordered early. Definition, the order-by math, and an example.
· 3 min read
Definition
What Is a Look-Ahead Schedule?
A look-ahead schedule breaks the next few weeks of the master schedule into the work each crew will do. Definition, an example, and how it differs.
· 3 min read
Definition
What Is a Notice to Proceed?
A notice to proceed is the owner's written go-ahead to start work, and often starts the contract time. Definition, a worked date example, NTP vs. award.
· 3 min read
Definition
What Is a Preliminary Notice?
A preliminary notice tells the owner and GC early that a sub or supplier is on the job and may claim a lien. Definition, two state rules, an example.
· 4 min read
Definition
What Is a Purchase Order in Construction?
A construction purchase order buys materials or equipment at stated prices, quantities and delivery terms. Definition, an example, PO vs. subcontract.
· 3 min read
Definition
What Is a Scope of Work in Construction?
A scope of work says what a contractor will and won't do, and which documents it rests on. Definition, an example, and scope vs. specifications.
· 3 min read
Definition
What Is a Shop Drawing?
A shop drawing shows exactly how a trade will fabricate and install part of the work, submitted for review before fabrication. Definition and an example.
· 4 min read
Definition
What Is a Subcontract?
A subcontract is the GC's contract with a sub for part of the prime contract's work. What it holds, and how it differs from a purchase order.
· 3 min read
Definition
What Is a Substitution Request?
A substitution request asks to use a product other than the one specified, with proof it is equal. Definition, an example, and or-equal vs. substitution.
· 3 min read
Definition
What Is a Takeoff in Construction?
A takeoff counts and measures every item of work on the drawings, the base of a bid. Definition, a worked drywall example, and takeoff vs. estimate.
· 3 min read
Definition
What Is a Unit Price in Construction?
A unit price is a fixed price per unit of measured work, paid on the quantity installed. Definition, a worked example, and the 15% quantity rule.
· 3 min read
Definition
What Is an Addendum in Construction?
An addendum is a written change to the bid documents issued before bids are due. Definition, an example, and how it differs from an ASI and a change order.
· 3 min read
Definition
What Is an Invitation to Bid in Construction?
An invitation to bid asks contractors to price defined work by a deadline. What it contains, an example, and how it differs from an RFP and an RFQ.
· 4 min read
Definition
What Is an O&M Manual?
An O&M manual tells the owner how to operate, maintain and repair a building's equipment and systems. Definition, what goes in one, and an example.
· 3 min read
Definition
What Is an OAC Meeting?
An OAC meeting is the regular owner-architect-contractor meeting during construction. What it covers, an example minutes item, and how it differs.
· 3 min read
Definition
What Is an RFI in Construction?
An RFI is a contractor's written question to the design team when the drawings or specs are unclear. Definition, an example, and what an RFI is not.
· 3 min read
Definition
What Is Cost to Complete?
Cost to complete is what is still to be spent to finish a job or budget line. Definition, the formula with projected final cost, and a worked example.
· 3 min read
Definition
What Is CSI MasterFormat?
CSI MasterFormat is the standard numbering for construction specifications, reused for bid packages, cost codes and closeout. Definition and an example.
· 3 min read
Definition
What Is Mobilization in Construction?
Mobilization is the work and cost of setting up on site before production starts, often paid as a lump-sum line. Definition, an example, demobilization.
· 3 min read
Definition
What Is Overhead and Profit (OH&P)?
Overhead and profit is the markup a contractor adds to direct cost. Definition, a worked example, and how OH&P differs from general conditions.
· 2 min read
Definition
What Is Subcontractor Prequalification?
Prequalification is a GC's review of a sub before inviting it to bid: finances, safety, experience, capacity. Definition, an example, and vs. onboarding.
· 3 min read
Definition
What Is the Warranty Period in Construction?
The warranty period is how long the contractor must fix defective work after completion. Definition, start dates, repaired work, and a worked example.
· 3 min read
Definition
What Is Time and Materials (T&M) in Construction?
Time and materials pays actual hours at agreed rates plus materials and equipment at cost plus markup. Definition, a priced ticket, and when it is used.
· 3 min read
Definition
What Is Value Engineering in Construction?
Value engineering delivers the same function for less without cutting what the owner needs. Definition, a federal savings-sharing example, VE vs. cuts.
· 3 min read
Construction
What Should a GC Do When a Sub Falls Behind?
What a GC does when a sub falls behind: measure it, talk, send written notice with a cure period, ask for a recovery plan, supplement, terminate.
· 7 min read
Preconstruction
What Should a Subcontract Agreement Include?
The clauses a construction subcontract agreement needs, what to check in each, how terms flow down from the prime contract, and a worked example.
· 8 min read
Preconstruction
When Should an Owner Hire an Owner's Rep?
When an owner should hire an owner's representative, what the rep does that the architect and GC don't, how reps are paid, and how to choose one.
· 6 min read
Preconstruction
Who Buys Builder's Risk Insurance on a Project?
Who buys builder's risk on a project, owner or contractor: how the contract decides it, what the policy should insure, and what to ask before you sign.
· 6 min read
Alternatives
BuildingConnected Alternatives for Sending Bids
Alternatives to BuildingConnected for sending trade bids, compared on who pays, published prices, bidder networks, leveling and what happens after award.
· 6 min read
Definition
Conditional vs Unconditional Lien Waiver
A conditional lien waiver takes effect only when payment clears; an unconditional one takes effect when signed. The difference, side by side, from statute.
· 3 min read
Construction
How Do Architects and Engineers Review a Submittal?
How the design team reviews a submittal: what the review covers and what it doesn't, choosing the review code, writing comments, and returning it on time.
· 8 min read
Closeout
How Do You Assemble a Construction Closeout Package?
A closeout checklist by spec section and company: O&M manuals, as-builts, warranties, attic stock, training, lien waivers. Build it at buyout. Example.
· 9 min read
Preconstruction
How Do You Build a Schedule of Values?
Split the contract sum into billable lines that follow the work, price each with its share of overhead and profit, and keep closeout real. With an example.
· 7 min read
Pricing explainer
How Much Does Procore Cost?
How Procore pricing works: an annual fee per product set by your construction volume, with unlimited users, and what to ask for in a quote.
· 5 min read
Construction
How to Write a Construction Daily Log (With Example)
How to write a construction daily log: what to record each day, a filled-in example, and the habits that make a log hold up in a delay claim.
· 6 min read
Bidding
How to Write a Scope of Work for a Subcontractor
Write a subcontractor scope of work from the drawings and specs: a summary, numbered inclusions, named exclusions, alternates and the documents behind it.
· 7 min read
Definition
What Are General Conditions in a Construction Bid?
General conditions in a bid are the contractor's cost of running the job: supervision, temporary facilities, site services. Not the A201 contract document.
· 4 min read
Definition
What Is Retainage in Construction?
Retainage is a percentage of each construction progress payment held back until the work is complete. Definition, an example, and how it differs.
· 3 min read
Alternatives
Best Construction Software for Small GCs
How a small GC should choose construction management software: six criteria, then seven products measured against them with their published prices.
· 6 min read
Definition
Bid Tabulation vs Bid Leveling: What's the Difference?
A bid tabulation records each bid as received; bid leveling adjusts each bid for scope gaps so all cover the same work. How they differ, with an example.
· 4 min read
Comparison
Conflo vs BuildingConnected for Bidding
Conflo and BuildingConnected compared for sending trade bids: who pays, published prices, leveling, the bidder network and what happens after award.
· 7 min read
Comparison
Conflo vs Procore for Small and Mid-Size GCs
Conflo vs Procore for small and mid-size general contractors: how each is priced, what each covers, where Procore is stronger, and who should choose which.
· 7 min read
Template
Free Three-Week Look-Ahead Schedule Template
A free three-week look-ahead schedule template in Excel: last week plus three weeks by day, crews, critical work and what must be ready. No email needed.
· 3 min read
Closeout
How Does an Architect Decide Substantial Completion?
How the architect inspects for substantial completion: the contractor's list, who walks, what blocks use and what is a punch item, and the certificate.
· 8 min read
Construction
How Should an Architect Respond to an RFI?
How the design team answers an RFI: check it against the documents, answer the question asked, cite the sheet and spec, and say if it changes the work.
· 8 min read
Bidding
Markup vs Margin: How Should a Contractor Price Work?
Markup is a percentage of cost; margin is a percentage of price. A 20% markup is a 16.7% margin. Conversion table and a worked remodel example.
· 5 min read
Money
Mechanic's Lien Deadlines: How They Work
How mechanic's lien deadlines are counted: the notices before, the filing deadline, the deadline to sue, and five states' filing deadlines from statute.
· 8 min read
Definition
ASI vs RFI: What Is the Difference?
ASI vs RFI: an RFI is the contractor's question about the documents; an ASI is the architect's written instruction or minor change, with no cost or time.
· 4 min read
Alternatives
Buildertrend Alternatives for Commercial Work
Buildertrend alternatives for commercial and residential contractors, compared on published price and pricing model, and when Buildertrend still wins.
· 5 min read
Template
Free Pay Application Template With Schedule of Values
A free Excel pay application: a summary sheet and a schedule of values with change orders, stored materials and retainage, calculated. No email needed.
· 4 min read
Template
Free RFI Template With a Filled-In Example
A free RFI template in Word, no email needed: every field a good request for information needs, a response section, and a filled-in example on page two.
· 4 min read
Closeout
How Do You Build a Punch List?
Build a punch list by walking the job room by room before substantial completion, logging each item with location, trade, photo and due date. With example.
· 9 min read
Construction
How Do You Build a Three-Week Look-Ahead Schedule?
How to build a three-week look-ahead from the master schedule: crew-sized pieces of work, what must be ready, and how to run it at the weekly meeting.
· 7 min read
Money
What Are Prompt Payment Acts in Construction?
Prompt payment acts set how fast owners and contractors must pay and what late payment costs. The federal act and five states' rules, with a timeline.
· 8 min read
Definition
What Is Substantial Completion?
Substantial completion is when the work is complete enough for the owner to use it as intended. What it triggers: retainage, warranties, delay damages.
· 3 min read
Template
Free Submittal Log Template (Excel)
A free submittal log template in Excel, no email needed: one row per spec item, with approve-by and submit-by dates worked out from lead times.
· 4 min read
Money
How Do You Price a Change Order?
Price a change order from direct cost (burdened labor, materials, equipment, sub quotes), then the markups and time your contract allows. Worked example.
· 9 min read
Preconstruction
How Do You Set Up a Submittal Log From the Specs?
Build a submittal log from the specs: one row per required item, section by section, with approve-by and submit-by dates worked back from the schedule.
· 10 min read
Construction
How Does an Architect Write an ASI?
How an architect writes an ASI: what it may change, the parts of a good one, a filled-in example, and when it must become a change order.
· 8 min read
Pricing explainer
How Much Does Buildertrend Cost?
Buildertrend's three plans (Essential, Advanced, Complete), their monthly prices as its pricing page listed them, what each adds, and yearly totals.
· 4 min read
Money
Texas Retainage Law: What Property Code Ch. 53 Says
Texas retainage from the statutes: the owner's 10% reserve, notice and lien deadlines for unpaid retainage, and the public-works caps of 10% and 5%.
· 9 min read
Definition
What Is a Punch List in Construction?
A punch list is the list of work still to be completed or corrected once a building is substantially complete. What goes on it, who writes it, an example.
· 3 min read
Definition
What Is Float in a Construction Schedule?
Float is how many working days an activity can slip. Total float vs free float, worked on a five-activity network, and who owns the float.
· 4 min read
Money
California Retainage Law: Private and Public Jobs
California retention rules from the statutes: the new 5% private cap from 2026, the 5% public cap, release deadlines and the 2% monthly penalty.
· 8 min read
Template
Change Order Pricing Calculator
A free change order pricing calculator (Excel): direct cost, markup on your own and subcontracted work, insurance and bond, to the cent. No email needed.
· 4 min read
Comparison
Conflo vs Microsoft Project for Construction Schedules
Conflo vs Microsoft Project for construction schedules: critical path, float, baselines, lookaheads, resources and file exchange, from their own pages.
· 6 min read
Bidding
How Do You Build an Estimate From Sub Bids?
Build a GC estimate from sub bids: plug each division, carry the leveled bid in place of the plug, add your own work and general conditions, then markups.
· 7 min read
Money
How Do You Calculate Retainage on a Pay App?
Retainage is a percentage of work completed and stored to date, held back each pay period. How to calculate it, reduce it, release it, with an example.
· 9 min read
Money
How Does a Subcontractor Write a Change Order Request?
A sub's change order request: notice first, then scope, priced direct cost, your markup, days and backup the GC can pass to the owner. Worked example.
· 9 min read
Comparison
Procore vs Buildertrend: Which Should You Buy?
Procore vs Buildertrend: who each is built for, how each is priced, what each includes, and which to buy for commercial or residential construction.
· 5 min read
Definition
What Is a Pay Application in Construction?
A pay application is a contractor's monthly request for payment against the schedule of values, less retainage and earlier payments. With an example.
· 3 min read
Definition
What Is a Transmittal in Construction?
A transmittal is the cover sheet that records what was sent, to whom, when and why, such as a submittal sent to the architect. The fields, with an example.
· 3 min read
Definition
What Is the Critical Path in Construction?
The critical path is the longest chain of linked activities in a construction schedule. A worked five-activity example, float, and what a delay does.
· 4 min read
Preconstruction
What Paperwork Does a GC Require From a Sub?
The documents a GC asks a subcontractor for before work and payment: W-9, insurance certificate and endorsements, license, safety program, waivers.
· 6 min read
Definition
Allowance vs Contingency: What Is the Difference?
An allowance is a set sum for a known item not yet chosen; a contingency is money for what nobody can foresee. How each is used and adjusted.
· 4 min read
Comparison
Conflo vs Buildertrend for Commercial Contractors
Conflo vs Buildertrend for commercial GCs: submittals, pay apps and retainage, bidding and pricing, and why Buildertrend is the pick for residential.
· 6 min read
Template
Free Bid Leveling Spreadsheet (Excel Template)
A free bid leveling spreadsheet for Excel: five bidders, fifteen scope rows, plugs and deducts, leveled totals, median and alternates. No email needed.
· 4 min read
Template
Free Punch List Template (Excel)
A free punch list template in Excel: location, description, company, trade, priority, photo, due date and status, with a status count. No email needed.
· 4 min read
Preconstruction
How Do You Buy Out a Construction Job?
Construction buyout step by step: scope review, leveling, award, the subcontract and its exhibits, compliance documents, and savings against budget.
· 7 min read
Money
How Do You Fill Out a Conditional Lien Waiver?
Fill out a conditional lien waiver field by field: the claimant, customer, through date, check details and exceptions, tied to the pay app's figures.
· 8 min read
Bidding
How Do You Level Subcontractor Bids?
Level subcontractor bids by pricing every scope gap, exclusion and missing addendum so each bid covers the same work, then compare the leveled totals.
· 9 min read
Bidding
How Do You Send an Invitation to Bid to Subs?
What an invitation to bid to subs includes, how to send it, and how to run questions and addenda so every bid prices the same scope, with an example.
· 7 min read
Money
How Does a GC Review a Subcontractor's Pay App?
Check each line against the field, stored materials against backup, change orders against approvals, then the math and the lien waivers. With an example.
· 7 min read
Money
Retainage Laws in the Five Largest Construction States
Retainage caps and release deadlines in California, Texas, Florida, New York and North Carolina, from each state's statutes, private and public.
· 10 min read
Definition
What Is a GMP Contract in Construction?
A GMP contract caps what the owner pays: the cost of the work plus a fee, up to a ceiling. A worked example of shared savings and an overrun.
· 4 min read
Definition
What Is a Submittal in Construction?
A submittal is what the contractor sends the design team to show how it will meet the specs: shop drawings, product data, samples. Types and an example.
· 4 min read
Preconstruction
AIA Contract Documents Explained, by Family
A plain map of AIA contract documents: the A, B, C, D, E, F and G series, the families by delivery method, and which forms you meet on a job.
· 8 min read
Definition
Change Order vs Construction Change Directive
A change order is an agreed change in scope, price and time; a construction change directive orders the work before price or time is agreed.
· 4 min read
Bidding
How Do You Break a Job Into Bid Packages?
Split a job into bid packages by trade: start from the CSI divisions, group what one kind of sub performs, and give every boundary item one home.
· 7 min read
Construction
How to Write an RFI in Construction (With an Example)
How to write an RFI in construction: the parts of a good request for information, a filled-in example, common mistakes, and how the RFI log works.
· 9 min read
Alternatives
Procore Alternatives for Small and Mid-Size GCs
Procore alternatives for small and mid-size general contractors, compared on published price, pricing model and commercial tools, with who each one suits.
· 6 min read
Template
Retainage Calculator for Pay Applications
Free retainage calculator: enter work to date and the rate to get retainage held, previous payments and the amount due, including a rate reduction.
· 3 min read
Definition
RFI vs Submittal: What Is the Difference?
An RFI asks the design team what the documents mean; a submittal shows how the contractor will meet them. The difference, side by side, with an example.
· 3 min read
Definition
What Is a Plug Number in a Bid?
A plug number is an estimator's own figure for work with no firm price yet: a placeholder in the estimate, or an add to a bid that excluded scope.
· 4 min read
Definition
What Is a Schedule of Values?
A schedule of values splits a construction contract sum into line items that every pay application bills against. Definition, example and how it differs.
· 3 min read
Closeout
What Should an Owner Get at Project Closeout?
The owner's closeout checklist: what you should get at substantial completion and before final payment, and how to check each document.
· 7 min read
How it works in Conflo
Conflo puts these phases on one platform: bidding, preconstruction, the field, financials and closeout, with your subs, the owner and the design team on the same project. Subcontractors, owners and architects join free, and every plan has unlimited users; plans and prices are on the pricing page.
A few connections that matter: awarding a trade bid opens a draft subcontract for the winner at the leveled amount; a change order can link to the RFI that caused it, and once executed it changes the contract sum on the pay apps; a sub's approved pay app rolls into the owner pay app; and the punch list carries into closeout alongside the closeout package, which can be delivered to the owner only when every document is approved.

The bottom line
A general contractor's job is to deliver the whole work and answer for it: price it, buy it out, build it to the documents, pay the people who build it, and hand over a finished building with its paper.
Each phase depends on the records kept in the one before it, so set them up at buyout and keep them current to the last day.
Sources
- FAR 52.246-12, Inspection of Construction — Acquisition.gov, U.S. General Services Administration. Read October 16, 2026.
- FAR 52.232-5, Payments under Fixed-Price Construction Contracts — Acquisition.gov, U.S. General Services Administration. Read October 16, 2026.
- FAR 52.232-27, Prompt Payment for Construction Contracts — Acquisition.gov, U.S. General Services Administration. Read October 16, 2026.
- The Construction Schedule – Substantial Completion Considerations — AIA Contract Documents (The American Institute of Architects). Read October 16, 2026.
- Summary: G704–2017, Certificate of Substantial Completion — AIA Contract Documents (The American Institute of Architects). Read October 16, 2026.
Questions
What are a general contractor's main responsibilities?
Delivering the whole work under its contract: pricing and winning the job, buying it out with subcontracts, planning submittals and the schedule, running the field, managing changes and the budget, billing the owner and paying subs, and closing out with a punch list, closeout package and warranties.
Is the general contractor responsible for subcontractors' work?
Usually yes. The GC contracts with the owner for the whole work and answers to the owner for its subs' work, while each sub answers to the GC under its subcontract. Your contract sets the details.
What is the difference between a general contractor and a construction manager?
A general contractor usually contracts to build for a price. A construction manager may advise the owner during design and, as construction manager at risk, then contracts to build, often for a guaranteed maximum price. The roles overlap; the contract defines them.
When does a general contractor's job end?
At final completion and final payment, once the punch list is closed and the closeout package delivered, and then the warranty period runs, commonly one year for the contractor's general warranty. Check your contract for the term and its start date.
Related
Pillar
The Construction Project Lifecycle: Bid to Closeout
The phases of a construction project, from planning and design to bidding, building and closeout, and what the owner, architect, GC and subs do in each.
· 7 min read
Role hub
The Subcontractor's Guide: Bidding to Getting Paid
Every step of a commercial job from the subcontractor's seat: bidding, the subcontract, submittals, RFIs, change orders, pay apps, retainage and closeout.
· 9 min read
Role hub
The Owner's Guide to a Commercial Building Project
The owner's role on a commercial building project, phase by phase: delivery method, choosing the contractor, pay apps, change orders and closeout.
· 7 min read
Role hub
The Architect's Guide to Construction Administration
The construction administration phase from the architect's seat: site visits, RFIs, ASIs, submittals, pay certification, changes and closeout.
· 8 min read