How Do You Do a Quantity Takeoff?

By Wyatt Cooper · Published · 7 min read

Key takeaways

  • A quantity takeoff turns the drawings and specifications into a list of measured items, each with a unit, that you can price.
  • Measure from the written dimensions, organize by area and by system, and put the sheet and detail on every line so anyone can check it.
  • Take off the net installed quantity first, then add waste as its own visible step, not hidden inside the measurement.
  • Check the total two ways before pricing: a ratio check (such as board per square foot of floor) against your past jobs, and a second person's count on the biggest items.

To do a quantity takeoff, first list your scope from the specifications and the invitation, then go sheet by sheet measuring each item from the written dimensions in its own unit: linear feet, square feet, cubic yards or each. Record the sheet and detail on every line, subtract openings, and total by area and by item. Add waste as a separate percentage, convert to purchase units like boards or sticks, and check the big items a second way before you price.

What a takeoff is for

The price of most trade work is quantity times a unit cost. The takeoff is the quantity half, and it is where many bad bids start: a missed wall type, a floor counted twice, a door schedule nobody read. The Defense Department's cost estimating criteria, UFC 3-740-05, put it plainly: the takeoff "must be as accurate as possible, and be based on available engineering and design data", and "equal emphasis is placed on both accurate quantity calculation and accurate pricing" (§3-3).

Before you measure, read the set the way reading drawings before you bid describes, so you know which sheets carry your work. The takeoff then feeds the price in your subcontractor proposal, and on a GC's job it is what a bid is compared on.

The method, step by step

  1. List the scope. Your specification sections, the invitation's scope of work and any alternates. Each becomes a heading in the takeoff.
  2. Pick a unit for each item and keep it: linear feet of wall or pipe, square feet of board or flooring, cubic yards of concrete, each for doors, fixtures and devices. UFC 3-740-05 asks for "standard units of measure and consistent with design units".
  3. Work sheet by sheet and area by area: one floor or zone at a time, the same order every time, marking each item on the drawing as you count it.
  4. Measure from the written dimensions, never by scaling a print. Where a dimension is missing, note an assumption and send a question.
  5. Subtract openings, but only those over the size your estimate's rule sets, and say what the rule is.
  6. Write the source on every line: sheet, detail and room. UFC 3-740-05 asks for takeoff computations kept as backup, each referencing the drawing and explaining the computation (§4-4).
  7. Add waste as a separate line. UFC 3-740-05 accepts either pricing waste into the unit cost or "increasing the measured quantity by waste and loss quantity" (if the excess quantity will not be used for any other purpose), and either way asks for a note saying which (§8-3).
  8. Convert to purchase units (boards, sticks, rolls, bags) and round up.
  9. Check it. A second count on the big items, or a ratio check (board per square foot of floor) against your past jobs.

A worked example: one partition type

A fictional tenant fit-out, with drywall partition type P1 on sheet A-101: 3-5/8 inch metal studs at 16 inches on center, one layer of 5/8 inch gypsum board each side, 10 feet high. The takeoff below is simplified (no corners, headers or blocking) to show the method. It takes the 120-foot wall from what a takeoff is further: there the wall is one straight run with 91 studs; here it is four runs, each counted on its own and rounded up, so it needs 95 before the door jambs are added.

Partition P1 runs measured from A-101 (fictional), studs at 16 inches on center
Run (A-101)LengthStud spaces (length × 12 ÷ 16, rounded up)Studs (spaces + 1)
Corridor wall, gridline 248 ft3637
Office 104 to 10636 ft2728
Conference 11022 ft17 (16.5 rounded up)18
Storage 11214 ft11 (10.5 rounded up)12
Total120 ft95

Takeoff: partition type P1, first floor (A-101, wall type detail 1/A-501)

Wall length
48 + 36 + 22 + 14 = 120 linear feet
Gross board area
120 ft × 10 ft = 1,200 square feet per side × 2 sides = 2,400 square feet
Openings
4 doors at 3 ft × 7 ft = 21 square feet each side; 4 × 21 × 2 = 168 square feet (door schedule, A-601)
Net board area
2,400 − 168 = 2,232 square feet
Waste
10% (the company's rule for this board size, noted in the estimate): 2,232 × 1.10 = 2,455.2 square feet
Board
2,455.2 ÷ 40 square feet per 4 × 10 sheet = 61.38, so 62 sheets
Studs
95 from the runs + 2 jamb studs per door × 4 doors = 103 studs
Track
Top and bottom: 120 × 2 = 240 ft, less 4 door openings × 3 ft at the bottom = 228 ft; in 10 ft lengths, 22.8, so 23 pieces
The rest of the P1 takeoff. Every quantity is for a fictional job and simplified.

Read the trail. Every number points to a sheet: the runs to A-101, the wall build to detail 1 on A-501, the doors to A-601. Waste is a visible 10%, not buried in a rounded-up length. Anyone checking the bid can follow it, and if an addendum moves the conference room wall, you change one line.

Mistakes that cost the job, or the margin

  • Taking off from the plans alone. Wall types, heights and fire ratings sit in the details, schedules and specs; the federal clause FAR 52.236-21 treats anything in either the drawings or the specifications "as if shown or mentioned in both".
  • Mixing net and gross. Decide whether a line is installed quantity or purchased quantity, and label it.
  • Counting a typical floor once. Multiply typical floors explicitly, and check the plans really are typical.
  • No sheet references. A takeoff without them can't be checked, updated for an addendum or defended after award.
  • Hiding assumptions. Write them down and send the questions; an assumption the GC never saw is not an exclusion.

On changed work later in the job, the same method prices the change: UFC 3-740-05 asks for "a separate quantity takeoff for each item directly affected" both before and after the change (§17-4.2), which is the backbone of pricing a change order. More for subs: the subcontractor's guide and the project lifecycle.

The bottom line

A takeoff is measured quantities in fixed units, by area and by item, each with its sheet reference, net first and waste added in the open.

Done that way, it can be checked, updated for an addendum in minutes and defended after award.

Join the waitlist

Sources

  1. UFC 3-740-05, Construction Cost Estimating (9 December 2022), §3-3 Quantities, §4-4, §8-3 Waste Allowance and §17-4.2 Changed Work — Department of Defense, Unified Facilities Criteria (Whole Building Design Guide). Read October 22, 2026.
  2. FAR 52.236-21, Specifications and Drawings for Construction, paragraph (a) — Acquisition.gov (General Services Administration). Read October 22, 2026.

Questions

What is a quantity takeoff in construction?

A list of every item of work measured from the drawings and specifications, each in a unit such as linear feet, square feet, cubic yards or each, ready to be multiplied by a unit cost to make a price.

What units are used in a takeoff?

The unit the work is installed and priced in: linear feet for walls, pipe and conduit; square feet for board, roofing and flooring; cubic yards for concrete and earthwork; each for doors, fixtures and devices. Keep one unit per item.

How much waste should I add to a takeoff?

Your company's rule for that material and job, from past jobs, added as a separate visible percentage. Federal estimating criteria accept waste either in the unit price or as added quantity, as long as a note says which.

Should I scale measurements off the drawings?

No. Use written dimensions. Prints are often reduced, and a scaled number is a guess. Where a dimension is missing, note your assumption and ask the GC or architect before bid day.

How do I check a takeoff?

Recount the largest items a second way or have someone else count them, and compare a ratio, such as board area per square foot of floor, with similar past jobs. Big differences mean a missed area or a double count.