The Architect's Guide to Construction Administration

By Wyatt Cooper · Published · 8 min read

Key takeaways

  • In construction administration the architect acts for the owner only as far as the contract says, and never controls the contractor's means, methods or safety.
  • Most of the phase is answering: RFIs, submittals and pay applications, each within the contract's time limits or with reasonable promptness.
  • The architect changes the work three ways: an ASI for minor changes with no cost or time, a change order, or a construction change directive.
  • Closeout runs through the architect too: the substantial completion inspection, the certificate, the warranties forwarded to the owner and the final certificate for payment.

The construction administration phase is the architect's and engineers' work from the construction contract to final payment: visiting the site, answering RFIs, reviewing submittals, issuing supplemental instructions, certifying the contractor's pay applications, preparing change orders, and inspecting for substantial and final completion. Under AIA A201–2017 the architect is the owner's representative during this phase, with only the authority the contract gives. This guide walks the phase in order and links every guide for the design team.

The architect's role in construction

Under the AIA general conditions, A201–2017, the architect "will provide administration of the Contract" and "will be an Owner's representative during construction until the date the final payment is due", acting for the owner "only to the extent provided in the Contract Documents" (§4.2.1). The same section draws the line every CA architect must hold: the architect "will not have control over, charge of, or responsibility for the construction means, methods, techniques, sequences or procedures, or for the safety precautions" (§4.2.2). Those are the contractor's.

Some owners add a layer. Connecticut's public works agency hires a separate construction administrator, and its CA procedure manual has that firm route "requests for clarifications and interpretations of the Contract Documents" to the architect, monitor payments and run meetings. Know whether your job has one, and which letters go through it.

Bidding and award: the documents everyone prices

Before construction administration starts, the design team's documents are priced. On a design-bid-build job the architect usually answers bidders' questions by addendum, issued to every bidder so that all of them price the same set; a question answered for one bidder only becomes a scope gap later. The owner may also ask you to help compare the bids or proposals that come back, line by line against the documents: the owner's side is in how to compare contractor proposals.

Which contract you administer depends on the delivery method. In design-bid-build you work for the owner and the contractor is hired separately; in design-build you may be the design-builder's consultant rather than the owner's; under construction manager at risk the CM often joins during design and prices it as it develops. See delivery methods compared, and which AIA family your agreement and the general conditions come from in AIA contract documents explained.

Before construction starts

  • Attend the preconstruction meeting and agree the channels. A201 §4.2.4 routes the architect's consultants through the architect and subcontractors through the contractor.
  • Approve the submittal schedule. Under §4.2.7 your review time runs from it; without one, "with reasonable promptness".
  • Agree the forms and numbering for RFIs, ASIs, proposal requests and change orders, and who signs each.
  • Set the site-visit rhythm with the owner: "at intervals appropriate to the stage of construction, or as otherwise agreed" (§4.2.2).

Site visits and field reports

Site visits are where construction administration is most often misread. Under §4.2.2 the architect visits to become "generally familiar with the progress and quality" of the work, to "endeavor to guard the Owner against defects and deficiencies", and to determine "in general" whether the work will conform when complete, but "will not be required to make exhaustive or continuous on-site inspections". Write field reports in those terms: what you observed, where and when, and what you are asking the contractor to correct.

Report what you find. Section 4.2.3 has the architect keep the owner "reasonably informed" and promptly report known deviations from the contract documents and the schedule, and defects observed. Section 4.2.6 gives the architect authority to reject nonconforming work and to require inspection or testing. Use both in writing, and keep the report with the photos.

  • Date, weather and who was on site, so the report can be placed on the schedule later.
  • What you looked at, by area and grid line, and what you didn't.
  • Each item that doesn't conform, with the sheet or spec section it departs from.
  • What you asked for: correction, an RFI from the contractor, a test or a submittal.
  • Open items from the last visit, closed or carried.

During construction: questions and submittals

The contractor's questions arrive as RFIs. The architect answers "in writing within any time limits agreed upon or otherwise with reasonable promptness" and, where appropriate, issues supplemental drawings and specifications (§4.2.14). For the contractor's side of the RFI, see how to write an RFI; for the difference between the two documents, ASI vs RFI.

Submittals are shop drawings, product data and samples. The architect reviews them "only for the limited purpose of checking for conformance with information given and the design concept" (§4.2.7), not for dimensions, quantities or means and methods, which stay with the contractor.

Both, step by step from the design team's seat: how to respond to an RFI, with the answer, the documents it relies on and whether it changes cost or time, and how to review a submittal, from the GC's review to your stamp. What should reach you, and what to send back when it doesn't, is in how a subcontractor prepares a submittal.

During construction: changes and payment

Changes take three forms (§7.1.2): the architect alone may order a minor change with no cost or time (an ASI; the AIA's form is G710); a change order is signed by owner, contractor and architect; a construction change directive is signed by owner and architect when the price isn't agreed yet. See how to write an ASI, and for pricing, how to price a change order.

Each month the contractor applies for payment, and within seven days of receiving it the architect certifies it in full, certifies a lesser amount with reasons, or withholds certification with reasons (§9.4.1). The certificate represents, to the best of the architect's knowledge, that the work has progressed to the point indicated and its quality conforms (§9.4.2). Know how the sub and GC build the application: how a subcontractor fills out a pay application and how retainage is calculated.

The checks to make before you sign, line by line against what you saw on site: how to certify a pay application. The owner reads the same application from its side, so expect its questions: how an owner reviews a GC's pay application.

Interpretations and decisions

Beyond answering RFIs, A201 makes the architect the first interpreter of the documents. Section 4.2.11 has the architect "interpret and decide matters concerning performance under, and requirements of, the Contract Documents" on written request of either party, and §4.2.12 requires those decisions to be consistent with the documents' intent, in writing, and impartial: the architect "will not show partiality to either". Decisions on aesthetic effect are final if consistent with that intent (§4.2.13). Write each one as you would want it read in a dispute: the question, the documents you relied on, and the decision.

Closeout

When the contractor believes the work is substantially complete, it sends the architect a list of items to finish or correct; the architect inspects, adds what isn't complete enough for the owner to use the building, and issues the certificate of substantial completion when it is (§9.8.2–9.8.4). The architect then receives and forwards the warranties to the owner and issues the final certificate for payment (§4.2.9). The contractor's side of that list is the punch list.

The phase doesn't quite end at final payment: §4.2.1 keeps the architect as the owner's representative "from time to time during the period for correction of Work", the one-year correction period after substantial completion. Your owner-architect agreement sets how much of that is in your fee, so read it.

The inspection itself, list in hand and room by room: how to determine substantial completion. What the owner should receive from it all, so you can check the package before you forward it: what an owner gets at closeout.

Every guide for architects and engineers

How it works in Conflo

In Conflo the design team works on the same project as the GC. RFIs routed to you wait in your court with a due date, and you answer on the record (RFIs). Submittals reach the architect after the GC's review step, if the GC sets one, and the architect's consultants after the architect; each reviewer returns approved, approved as noted, revise and resubmit, or rejected (Submittals). You issue sets, ASIs and bulletins in Drawings, where each reissued sheet supersedes its old revision.

Conflo does not certify pay applications for the architect or prepare a certificate of substantial completion today; those stay on your own forms.

A plumbing product-data submittal on its second revision in Conflo: in design review with the architect and due in two days, the description and spec section, files, and the GC's review approving it and forwarding it on.
A plumbing submittal in Conflo after the GC's review, in design review with the architect and due in two days.

The bottom line

Construction administration is answering in writing, on time, within the authority the contract gives you: RFIs, submittals, minor changes, pay certifications and the closeout inspections, without ever taking over the contractor's means and methods.

If your RFIs and submittals arrive by email from five GCs, join the Conflo waitlist as a design team.

Join the waitlist

Sources

  1. Summary: A201–2017, General Conditions of the Contract for Construction — AIA Contract Documents. Read October 17, 2026.
  2. 0600 Construction Administrator's Procedure Manual — State of Connecticut Department of Administrative Services. Read October 16, 2026.
  3. Instructions: G710–2017, Architect's Supplemental Instructions — AIA Contract Documents. Read October 16, 2026.

Questions

What is the construction administration phase?

The last phase of an architect's basic services, from the start of construction to final payment: site visits, RFIs, submittal review, supplemental instructions, pay application certification, change orders and the completion inspections. The owner-architect agreement defines its scope.

Does the architect supervise the contractor?

No. Under AIA A201–2017 §4.2.2 the architect visits the site to become generally familiar with the work and guard the owner against defects, but has no control over the contractor's means, methods, sequences or safety, and isn't required to inspect exhaustively.

How long does an architect have to certify a pay application?

Under A201–2017 §9.4.1, seven days after receiving the contractor's application, to certify it in full, certify part with reasons, or withhold certification with reasons. Your contract may set a different period.

Who decides substantial completion?

Under A201–2017 the architect inspects after the contractor submits its list, and issues the certificate of substantial completion once the work is complete enough for the owner to occupy or use it for its intended purpose (§9.8).