How Do You Make a Miller Act Payment Bond Claim?
By Wyatt Cooper · Published · 8 min read
Key takeaways
- On federal construction contracts above the threshold, the prime contractor furnishes a payment bond, and unpaid subs and suppliers claim against that bond.
- A sub or supplier with a contract directly with the prime can sue on the bond if not paid in full within 90 days after its last labor or material.
- A second-tier sub or supplier (with a contract with a sub, not the prime) must first give the prime written notice within 90 days after its last labor or material.
- Every claimant must sue no later than one year after its last labor or material, in federal district court where the contract was performed; in the worked example, notice by June 11, 2026 and suit by March 13, 2027 (a Saturday, so file by Friday, March 12).
To make a Miller Act payment bond claim, find your date of last labor or material. If you contracted with a subcontractor rather than the prime, send the prime contractor written notice within 90 days of that date, stating the amount and whom you supplied. If you contracted with the prime, you may sue once 90 days pass unpaid. Either way, file suit in the federal district court where the contract was performed within one year of that date.
Why federal jobs have payment bonds
On private work, an unpaid sub's main protection is often a mechanics lien. On federal work, the statute's protection is a payment bond. Under 40 U.S.C. § 3131, before a contract of more than $100,000 is awarded for the construction, alteration or repair of a public building or public work of the Federal Government, the contractor must furnish a performance bond and a payment bond, the payment bond for the protection of all persons supplying labor and material in carrying out the work (40 U.S.C. § 3131). The Federal Acquisition Regulation applies the requirement to construction contracts exceeding $150,000, and requires other payment protections for contracts above $35,000 up to $150,000 (FAR 28.102-1).
You can get a copy of the bond. Section 3133(a) says the agency shall furnish a certified copy of the payment bond and the contract to anyone who submits an affidavit that they supplied labor or material for the work and have not been paid, or that they are being sued on the bond; the applicant pays the agency's fee (40 U.S.C. § 3133). The copy names the surety you will be claiming against.
Who can claim, and what each must do
| Who you are | Notice before suit | When you may sue | Last day to sue |
|---|---|---|---|
| First tier: a contract directly with the prime contractor | None required by the statute | If not paid in full within 90 days after your last labor or material | One year after your last labor or material |
| Second tier: a contract with a subcontractor, none with the prime | Written notice to the prime within 90 days from your last labor or material | After giving that notice | One year after your last labor or material |
The statute names these two groups. If your contract is with a supplier to a sub, or a sub further down, ask a lawyer whether you are covered before you rely on the bond. The second-tier notice must state (the codified text says "the action"; it is read as the notice) with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or for whom the labor was done. It must be served by any means that provides written, third-party verification of delivery to the contractor at any place it maintains an office or conducts business or at its residence, or in any manner in which the U.S. marshal of the district may serve summons (§ 3133(b)(2)).
The suit must be brought in the name of the United States for the use of the person bringing it, in the U.S. District Court for any district in which the contract was to be performed and executed, regardless of the amount in controversy (§ 3133(b)(3)). The Government is not liable for the costs of the suit (§ 3133(b)(5)).
Step by step
- 1ClaimantWrites down the date of its last labor or material and the unpaid amount
- 2ClaimantRequests a certified copy of the payment bond from the agency, with an affidavit
- 3ClaimantSends written notice to the prime within 90 days, with third-party proof of delivery
- 4Prime and suretyPay, dispute or ignore the claim
- 5ClaimantFiles suit in federal district court within one year of its last labor or material
- Keep the records that prove the date: daily logs, delivery tickets, time sheets. The statute runs from the day you did or performed the last of the labor or furnished the last of the material for which the claim is made.
- Count the days yourself, and send notice weeks early. The statute's text has no rule moving a deadline that falls on a weekend or holiday.
- Send notice by a carrier that gives a signed delivery receipt, to the prime's office, and keep the receipt.
- Keep billing and asking for payment while you wait; the bond is a backstop, not a reason to stop collecting.
A worked example: a dated timeline for a second-tier supplier
The facts are fictional. "Kestrel Supply" sells $36,400.00 of light fixtures to "Brightline Electric", the electrical sub on a federal courthouse renovation. Kestrel has no contract with the prime contractor. Its last delivery for the job is on Friday, March 13, 2026, and Brightline doesn't pay.
| Event | Rule | Date |
|---|---|---|
| Last material furnished | Starts both clocks | Friday, March 13, 2026 |
| Notice to the prime: last day | Within 90 days from the last material (§ 3133(b)(2)) | Thursday, June 11, 2026 (day 90) |
| Target date to send notice | Weeks early, with delivery tracking | Monday, May 18, 2026 |
| Suit: last day | No later than one year after the last material (§ 3133(b)(4)) | Saturday, March 13, 2027 |
| Target date to file suit | Before the weekend, and well before | No later than Friday, March 12, 2027 |
The count: March 14 to 31 is 18 days, April adds 30 (48), May adds 31 (79), and June 1 to 11 adds 11, so June 11 is day 90. One year after March 13, 2026 is March 13, 2027, a Saturday; because the statute's text doesn't move it, Kestrel plans to file by Friday, March 12.
Notice of claim on payment bond, 40 U.S.C. § 3133(b)(2)
- To
- The prime contractor, at its office address, by courier with signed delivery receipt
- Project
- Federal courthouse renovation, contract number as shown on the bond (fictional)
- Claimant
- Kestrel Supply (fictional)
- Furnished to
- Brightline Electric (fictional), electrical subcontractor
- Amount claimed
- $36,400.00 for light fixtures, last furnished March 13, 2026
- Attached
- Invoices, delivery tickets, statement of account
- Sent
- May 18, 2026
Waivers of bond rights
A GC or sub may ask you to waive your bond rights in a subcontract or purchase order. Under § 3133(c), a waiver of the right to bring a civil action on a payment bond is void unless it is in writing, signed by the person whose right is waived, and executed after that person has furnished labor or material for use in the performance of the contract (40 U.S.C. § 3133). Read any lien or bond waiver that comes with a payment; the difference between conditional and unconditional waivers is in conditional vs unconditional lien waivers.
Payment deadlines on federal work are in prompt payment acts, how a pay-if-paid clause interacts with your rights is in pay-if-paid vs pay-when-paid, and habits that keep you from needing the bond are in how a subcontractor can get paid faster and the subcontractor's guide.
The bottom line
A Miller Act claim runs on two dates counted from your last labor or material: 90 days for a second-tier claimant's written notice to the prime, and one year for every claimant's suit in federal district court.
Write the date down on the day it happens, get a copy of the bond early, and send notice weeks before day 90 with proof of delivery.
Sources
- 40 U.S.C. § 3131, Bonds of contractors of public buildings or works — U.S. Government Publishing Office (govinfo), United States Code, 2023 edition. Read October 22, 2026.
- 40 U.S.C. § 3133, Rights of persons furnishing labor or material — U.S. Government Publishing Office (govinfo), United States Code, 2023 edition. Read October 22, 2026.
- FAR 28.102-1, General (bonds for construction contracts) — Acquisition.gov, U.S. General Services Administration. Read October 22, 2026.
Questions
Who can make a Miller Act claim?
Under 40 U.S.C. § 3133(b), a person who furnished labor or material under a contract directly with the prime contractor, or under a contract with a subcontractor of the prime. The second group must first give the prime written notice within 90 days.
What is the Miller Act notice deadline?
For a claimant with no contract with the prime, written notice to the prime within 90 days from the date it did the last of the labor or furnished the last of the material for which the claim is made.
How long do you have to file a Miller Act lawsuit?
No later than one year after the day the claimant last performed labor or supplied material, in the U.S. District Court for a district where the contract was to be performed and executed.
Which federal contracts need a payment bond?
The statute requires one before a contract of more than $100,000 is awarded for construction, alteration or repair of a federal public building or work; the FAR applies the bond requirement to construction contracts exceeding $150,000 and requires other payment protections for contracts above $35,000 up to $150,000.
Can I waive my Miller Act rights in a subcontract?
A waiver is void unless it is in writing, signed by you, and executed after you have furnished labor or material for the contract, under 40 U.S.C. § 3133(c).
Related
Money
What Are Prompt Payment Acts in Construction?
Prompt payment acts set how fast owners and contractors must pay and what late payment costs. The federal act and five states' rules, with a timeline.
· 8 min read
Money
Pay-if-Paid vs Pay-When-Paid: What Do They Mean?
Pay-if-paid shifts the risk of owner nonpayment to the sub; pay-when-paid only sets timing. How to tell them apart, and three state statutes on them.
· 8 min read
Money
How Can a Subcontractor Get Paid Faster?
Subcontractors get paid faster by billing on the GC's cutoff, sending clean pay apps and waivers, and using the prompt-pay dates that start the clock.
· 6 min read
Money
Mechanic's Lien Deadlines: How They Work
How mechanic's lien deadlines are counted: the notices before, the filing deadline, the deadline to sue, and five states' filing deadlines from statute.
· 8 min read
Role hub
The Subcontractor's Guide: Bidding to Getting Paid
Every step of a commercial job from the subcontractor's seat: bidding, the subcontract, submittals, RFIs, change orders, pay apps, retainage and closeout.
· 9 min read