What Are Liquidated Damages in Construction?
By Wyatt Cooper · Published · 3 min read
Key takeaways
- Liquidated damages (LDs) replace proving the owner's actual delay losses with a daily rate agreed up front.
- The rate must be a reasonable forecast of the owner's harm; a rate set to punish is a penalty and may not be enforced.
- LDs run from the contract completion date, adjusted for approved time extensions, to the day the work is completed or accepted.
Liquidated damages (LDs) are usually a fixed amount per calendar day, agreed in the contract, that the contractor pays the owner for each day the work finishes late. The rate is a reasonable forecast, made in advance, of the owner's real losses, such as lost rent, which would be hard to prove later. LDs compensate; they are not a penalty.
When liquidated damages fit
Federal policy allows them only when timely performance is "so important that the Government may reasonably expect to suffer damage if the delivery or performance is delinquent" and the damage "would be difficult or impossible to estimate accurately or prove," and the rate "must be a reasonable forecast of just compensation for the harm that is caused by late delivery or untimely performance" (FAR 11.501). The construction clause charges a stated amount "for each calendar day of delay until the work is completed or accepted" (FAR 52.211-12).
LDs at $1,500 per calendar day
- Contract completion date
- June 30
- Approved time extension
- 6 days, to July 6
- Work completed and accepted
- July 20
- Days late
- July 6 to July 20 = 14 days
- Liquidated damages
- 14 × $1,500 = $21,000
LDs, actual damages and penalties
With LDs, the owner collects the agreed rate without proving its losses, and usually can't collect more for the same delay. Without an LD clause, the owner must prove actual damages. A rate far above any likely loss reads as a penalty, which courts generally won't enforce. Many contracts also stop LDs at substantial completion rather than final completion, so how that date is set matters: see how to determine substantial completion.
The clock starts with the notice to proceed. Subcontracts often pass LDs down to the trade that caused the delay, so a schedule that shows float and the critical path is the best evidence of who did.
The bottom line
Liquidated damages are a daily price for finishing late, agreed before the job so nobody has to prove the loss after it.
Owners: set the rate from your real costs of delay and write the calculation down. Book a demo to see Conflo.
Sources
- FAR 11.501, Policy (liquidated damages) — Acquisition.gov, U.S. General Services Administration. Read October 22, 2026.
- FAR 52.211-12, Liquidated Damages—Construction — Acquisition.gov, U.S. General Services Administration. Read October 22, 2026.
Questions
Do liquidated damages apply if the owner caused the delay?
Generally not for days the owner caused. The contractor should request a time extension in writing, as the contract requires, so the completion date moves before LDs are counted.
Can a GC pass liquidated damages to a subcontractor?
If the subcontract says so, usually for delay the sub caused, often capped at what the owner assesses. Read the subcontract's delay clause before signing.
Related
Definition
What Is Substantial Completion?
Substantial completion is when the work is complete enough for the owner to use it as intended. What it triggers: retainage, warranties, delay damages.
· 3 min read
Definition
What Is a Notice to Proceed?
A notice to proceed is the owner's written go-ahead to start work, and often starts the contract time. Definition, a worked date example, NTP vs. award.
· 3 min read
Closeout
How Does an Architect Decide Substantial Completion?
How the architect inspects for substantial completion: the contractor's list, who walks, what blocks use and what is a punch item, and the certificate.
· 8 min read
Construction
How Should an Owner Respond to a GC's Delay Claim?
An owner's first 30 days after a contractor's delay claim: check the notice, sort the days by cause, test the schedule and money, answer in writing.
· 6 min read
Role hub
The Owner's Guide to a Commercial Building Project
The owner's role on a commercial building project, phase by phase: delivery method, choosing the contractor, pay apps, change orders and closeout.
· 7 min read