How Do You Calculate Concrete for a Slab?
By Wyatt Cooper · Published · 6 min read
Key takeaways
- Cubic yards of concrete are length times width times thickness, all in feet, divided by 27, because a cubic yard is 3 feet by 3 feet by 3 feet.
- Convert inches to feet before you multiply: a 4-inch slab is 4 ÷ 12 = 0.333 feet thick, not 4.
- Add each shape separately (slab, continuous footings, round piers), then order more than the plan quantity; the ready-mix industry's guidance is 4% to 10% more.
- Thickness drives the overrun: an eighth of an inch extra on a 4-inch slab is about 3% more concrete.
To calculate concrete for a slab, multiply its length and width in feet by its thickness in feet (inches divided by 12), then divide the cubic feet by 27 to get cubic yards. A 24 by 24 foot slab 4 inches thick is 24 × 24 × 0.333 = 192 cubic feet, or 7.11 cubic yards. Add footings and piers the same way, then order 4% to 10% more for uneven subgrade, form movement and waste.
The formula, shape by shape
Ready mixed concrete "is sold by volume, in cubic yards (cubic meters)," as the National Ready Mixed Concrete Association puts it in CIP 31, Ordering Ready Mixed Concrete. A cubic yard is 27 cubic feet (3 × 3 × 3), which is why the industry's own yield formula divides by 27 (CIP 8, Discrepancies in Yield). Work every dimension in feet, find the cubic feet of each shape, add them, and divide once.
| Shape | Cubic feet | Watch for |
|---|---|---|
| Slab | Length × width × thickness | Thickness in feet: 4 in = 0.333 ft, 5 in = 0.417 ft, 6 in = 0.5 ft |
| Continuous footing or grade beam | Total run length × width × depth | Measure the run on the centerline so corners aren't counted twice |
| Thickened slab edge | Perimeter × added width × added depth | Only the part below the slab's own thickness |
| Round pier or caisson | 3.1416 × radius² × depth, times the count | Radius is half the diameter, in feet: a 12-inch pier is 0.5 ft |
| Wall | Length × height × thickness | Subtract openings larger than you will waste anyway |
Take dimensions from the structural drawings, not the architectural plan, and use the detail's thickness, which may be more at edges, under bearing walls or at equipment pads. If you bid the job as a concrete sub, the same takeoff feeds your unit prices; see how concrete subs bid and bill.
Worked example: a slab, footings and piers
A fictional detached garage: a 24 by 24 foot slab, 4 inches thick; a continuous footing 16 inches wide and 8 inches deep in a 96-foot centerline run; and twelve 12-inch round piers, 4 feet deep, for a porch.
Garage concrete takeoff
- Slab
- 24 × 24 × (4 ÷ 12) = 192.00 cu ft
- Footing
- 96 × (16 ÷ 12) × (8 ÷ 12) = 12,288 ÷ 144 = 85.33 cu ft
- Piers
- 12 × 3.1416 × 0.5² × 4 = 37.70 cu ft
- Total
- 192.00 + 85.33 + 37.70 = 315.03 cu ft
- Cubic yards
- 315.03 ÷ 27 = 11.67 cu yd
- Plus 5%
- 11.67 × 1.05 = 12.25 cu yd
- Plus 10%
- 11.67 × 1.10 = 12.84 cu yd
- Order
- Between 12.25 and 12.84 cu yd, rounded up to what your supplier sells
Check it a second way: the slab alone is 7.11 cubic yards (192 ÷ 27), the footing 3.16 and the piers 1.40, which add to 11.67. At this size the order is more than one truck can carry if trucks run 8 to 12 cubic yards (CIP 31), so ask the producer how they will split it and pour the footing and piers first.
How much extra to order, and why
NRMCA's guidance is that the "quantity of concrete ordered should be 4% to 10% more than an estimate calculated from the plan dimensions to account for contingencies" (CIP 31). Its yield bulletin lists why forms take more than the plan says: thickness or dimensions bigger than assumed "even by a small amount," forms that deflect under the concrete's pressure, and "placement on irregular subgrade or granular fill and settlement" (CIP 8).
- Thickness first. CIP 8's example: a 1/8-inch difference on a 4-inch slab means a 3% shortage, or 1 cubic yard on a 32-yard order. On the garage slab, 4 1/8 inches is 7.33 cubic yards instead of 7.11.
- Subgrade next. Fine-grade and compact the base, and check it with a string line before the pour.
- Forms. Brace them; a bowed form adds volume you never measured.
- Small leftovers count. Concrete returned each day or used in mud sills and small footings adds up over a job (CIP 8).
Use the low end of the range for formed work you can measure, such as walls, and the high end for slabs on uneven ground and for drilled piers in loose soil. Then order once, with a clean-up load as a last resort: CIP 31 advises avoiding "excessive concrete or small clean-up loads."
What else to tell the plant
The volume is one line of the order. CIP 31 lists what else the producer needs: the size of coarse aggregate, the slump, air content where the concrete is exposed to freezing, the strength or performance requirement (it gives 3,500 to 5,000 psi as typical for most applications), and the delivery address, placement method, rate and time. A loaded truck weighs about 80,000 pounds and "may not be able to maneuver on loose dirt or over residential curbs," so plan the access or a pump.
Write the quantity and the waste factor on the estimate, so a change in slab thickness or footing depth can be priced from the same math. Price the concrete as a cost, then the markup, the way markup vs margin explains.
The bottom line
Concrete is length times width times thickness in feet, divided by 27, shape by shape, then 4% to 10% more for the subgrade, the forms and the pour. Measure thickness carefully, because it moves the number most.
If you are a sub bidding the work, carry the takeoff into your unit prices and billing; the subcontractor's guide covers the rest.
Sources
- CIP 31, Ordering Ready Mixed Concrete — National Ready Mixed Concrete Association. Read October 22, 2026.
- CIP 8, Discrepancies in Yield — National Ready Mixed Concrete Association. Read October 22, 2026.
Questions
How many cubic yards of concrete do I need for a 10 by 10 slab?
At 4 inches thick, 10 × 10 × 0.333 = 33.3 cubic feet, divided by 27 is 1.23 cubic yards. Ordering 4% to 10% more gives about 1.28 to 1.36 cubic yards, rounded up to what your supplier sells.
Why do you divide by 27 to get cubic yards?
A cubic yard is a cube 3 feet on each side, so it holds 3 × 3 × 3 = 27 cubic feet. Find the volume in cubic feet, then divide by 27.
How much extra concrete should I order?
The ready-mix industry's guidance (NRMCA's CIP 31) is 4% to 10% more than the volume from the plan dimensions, for uneven subgrade, form movement, spillage and small differences in thickness.
How do I calculate concrete for a round pier?
Multiply 3.1416 by the radius squared and by the depth, all in feet, then by the number of piers. Twelve 12-inch piers 4 feet deep are 12 × 3.1416 × 0.25 × 4 = 37.7 cubic feet, or 1.40 cubic yards.
Why did my slab need more concrete than I ordered?
Usually because it was thicker than planned, the subgrade was uneven, or forms bowed. A 1/8-inch difference on a 4-inch slab is about a 3% shortage. Fine-grade the base and check the thickness before the pour.
Related
Bidding
How Concrete Subs Bid and Bill Commercial Work
How a concrete subcontractor bids and bills commercial work: lump sum vs unit prices, the testing before and after each pour, and a worked pay app.
· 7 min read
Bidding
Markup vs Margin: How Should a Contractor Price Work?
Markup is a percentage of cost; margin is a percentage of price. A 20% markup is a 16.7% margin. Conversion table and a worked remodel example.
· 5 min read
Bidding
How to Write a Sub Proposal a GC Can Level
Write a subcontractor bid proposal the GC can level: match its scope items, break out prices, price exclusions, and see what the GC does with each line.
· 7 min read
Role hub
The Subcontractor's Guide: Bidding to Getting Paid
Every step of a commercial job from the subcontractor's seat: bidding, the subcontract, submittals, RFIs, change orders, pay apps, retainage and closeout.
· 9 min read
