Pay-if-Paid vs Pay-When-Paid: What Do They Mean?
By Wyatt Cooper · Published · 8 min read
Key takeaways
- A pay-if-paid clause makes the owner's payment to the GC a condition of the GC paying the sub: if the owner never pays, the sub may never be paid.
- A pay-when-paid clause is about timing: the GC pays the sub within a set time after the owner pays, but the owner's failure to pay does not cancel the debt.
- Read for the words: "condition precedent" and "only if" point to pay-if-paid; "within 7 days after receipt" alone points to timing.
- Some states limit these clauses by statute: North Carolina makes pay-if-paid unenforceable, Wisconsin voids it but allows delay, and Nevada sets payment deadlines a contract cannot waive.
Pay-if-paid and pay-when-paid are subcontract payment clauses. Pay-if-paid makes the owner's payment to the general contractor a condition precedent to the GC paying the subcontractor, so the sub bears the risk if the owner never pays. Pay-when-paid only sets when the GC pays, such as within seven days after it is paid, and the sub is still owed if the owner doesn't pay. Some states limit or void pay-if-paid clauses by statute.
Two clauses that look alike
Both clauses tie the sub's payment to the owner's payment to the GC, which is why they are confused. The difference is what happens when the owner never pays. Under pay-if-paid, the GC's duty to pay the sub depends on the owner's payment; under pay-when-paid, it is only delayed by it. That difference decides who carries the risk of an owner going broke or refusing to pay.
| Question | Pay-if-paid | Pay-when-paid |
|---|---|---|
| What it does | Makes the owner's payment a condition of the sub's payment | Sets when the sub is paid after the owner pays |
| Owner pays late | Sub is paid when the GC is paid | Sub is paid when the GC is paid |
| Owner never pays | Sub may never be paid by the GC under the clause | The clause sets timing only; the GC's debt is not canceled |
| Typical wording | "Payment by the owner is a condition precedent"; "only if and to the extent paid" | "Within 7 days after the contractor receives payment" |
| Who carries the owner's credit risk | The subcontractor | The GC |
| Where it may be limited | Statutes in some states, such as North Carolina and Wisconsin | Prompt payment statutes set deadlines in many states |
How to read the clause in your subcontract
- Find the payment article, and any clause that mentions the owner's payment, condition precedent or risk of nonpayment.
- Look for condition words: "condition precedent", "only if", "if and only to the extent", or a sentence saying the sub accepts the risk that the owner will not pay. These point to pay-if-paid.
- Look for timing words alone: "within 7 days after receipt of payment". With no condition words, this reads as pay-when-paid.
- Check which state's law the subcontract chooses, and where the project is; a statute where the project is may override the clause.
- Note your backstops: lien rights on private work, and payment bond rights on public work, such as a Miller Act claim on federal jobs. Their deadlines run whatever the clause says.
If you can, negotiate before you sign: change a condition precedent into a timing clause with an outside date. The example below is illustration only, not model contract language.
Subcontract payment clause, marked up by the subcontractor
- As drafted
- Receipt of payment by Contractor from Owner is a condition precedent to Contractor's obligation to pay Subcontractor.
- What it does
- Pay-if-paid: the sub carries the risk that the owner never pays
- As marked up
- Contractor shall pay Subcontractor within 7 days after Contractor receives payment for Subcontractor's work, and in any event within 45 days after Subcontractor's application.
- What it does
- Pay-when-paid with an outside date: timing only, with a last day that doesn't depend on the owner
What three state statutes say
North Carolina: General Statutes § 22C-2 says that performance by a subcontractor in accordance with its contract entitles it to payment from the party with whom it contracts, that payment by the owner to a contractor is not a condition precedent for payment to a subcontractor, and that an agreement to the contrary is unenforceable (N.C. Gen. Stat. § 22C-2).
Wisconsin: Statutes § 779.135(3) makes void, in contracts for the improvement of land in the state, provisions that make a payment to a prime contractor from any person who has no contract with the subcontractor, supplier or service provider a condition precedent to the prime contractor's payment to them. It also says it does not prohibit provisions that may delay a payment until the prime contractor receives payment from that person (Wis. Stat. § 779.135). In plain words: pay-if-paid is void; pay-when-paid timing is allowed.
Nevada: NRS 624.624 sets the deadline itself. Under a written agreement with a payment schedule, the higher-tiered contractor must pay the lower-tiered subcontractor on or before the date payment is due, or within 10 days after it receives payment for the work in the sub's request, whichever is earlier; under an agreement without a schedule, or an oral one, within 30 days after the sub's request or within 10 days after receiving payment, whichever is earlier. NRS 624.628(3) makes void a provision that requires a lower-tiered subcontractor to waive or limit those rights (NRS chapter 624).
States are not named here unless their statute was read for this page. Other states have prompt payment statutes that set deadlines between tiers; five are summarized in prompt payment acts.
A worked example: the same unpaid bill under each clause
The facts are fictional. A drywall sub bills $48,000.00 for March on a private job. Its subcontract has a payment schedule with payment due April 30. The owner pays the GC nothing for March because of a dispute with the GC that has nothing to do with the sub's work.
| Clause and place | What the words say | What the sub can expect |
|---|---|---|
| Pay-if-paid, in a state with no statute on it | Owner's payment is a condition precedent | The GC may argue it owes nothing until the owner pays; the sub looks to its lien or bond rights |
| Pay-when-paid, same state | GC pays within 7 days after it is paid | The clause sets timing; the GC still owes the $48,000.00, and when it is due depends on the clause and state law |
| Any condition precedent, job in North Carolina | § 22C-2: an agreement to the contrary is unenforceable | The GC owes the sub for performance under the subcontract |
| Pay-if-paid, job in Wisconsin | § 779.135(3): condition precedent void, delay allowed | The condition is void; a delay provision may still set timing |
| Any clause, job in Nevada, written schedule | NRS 624.624(1)(a): due date or 10 days after GC is paid, whichever is earlier | Due April 30, the scheduled date, since the GC was not paid sooner |
Change one fact in the Nevada row: if the owner had paid the GC for the sub's work on April 12, the statute's earlier date would be 10 days later, April 22, before the April 30 schedule date. Nevada also lets the GC withhold some amounts under conditions and notices the statute sets, including a retention amount of no more than 5 percent of the payment (NRS 624.624).
The bottom line
Pay-if-paid moves the risk of owner nonpayment to the sub; pay-when-paid only sets the timing. Read your payment clause for condition words before you sign, and check whether a statute where the job is limits it.
Whatever the clause says, keep your lien and bond deadlines; they are the protection that does not depend on the owner paying the GC. More on getting paid is in how a subcontractor can get paid faster and the subcontractor's guide.
Sources
- N.C. Gen. Stat. § 22C-2, Performance by subcontractor — North Carolina General Assembly. Read October 22, 2026.
- Wis. Stat. § 779.135, Construction contracts, form of contract — Wisconsin State Legislature. Read October 22, 2026.
- NRS Chapter 624, Contractors (NRS 624.624 and 624.628) — Nevada Legislature. Read October 22, 2026.
Questions
What is the difference between pay-if-paid and pay-when-paid?
Pay-if-paid makes the owner's payment a condition of the sub being paid, so the sub carries the risk that the owner never pays. Pay-when-paid only sets the timing of the sub's payment after the owner pays; the GC still owes the sub if the owner doesn't.
Are pay-if-paid clauses enforceable?
It depends on the state. North Carolina's § 22C-2 makes an agreement that the owner's payment is a condition precedent unenforceable, and Wisconsin's § 779.135(3) voids such provisions. Elsewhere it turns on the clause's words and the state's law.
How do I know if my subcontract has a pay-if-paid clause?
Look for "condition precedent", "only if", "if and to the extent" or a sentence saying you accept the risk of the owner's nonpayment. A clause that only says when you are paid after the GC is paid is usually read as timing.
Does a pay-if-paid clause affect my lien or bond rights?
Your lien and payment bond deadlines keep running under their own statutes, whatever the payment clause says. Wisconsin's § 779.135(1) separately voids provisions requiring a waiver of lien or bond rights before you are paid.
Can a GC delay payment under a pay-when-paid clause forever?
Generally not; a timing clause delays payment, it does not cancel it. Some states set the deadline by statute; Nevada's NRS 624.624, for example, sets due dates that a contract cannot waive.
Related
Money
What Are Prompt Payment Acts in Construction?
Prompt payment acts set how fast owners and contractors must pay and what late payment costs. The federal act and five states' rules, with a timeline.
· 8 min read
Money
How Can a Subcontractor Get Paid Faster?
Subcontractors get paid faster by billing on the GC's cutoff, sending clean pay apps and waivers, and using the prompt-pay dates that start the clock.
· 6 min read
Money
How Do You Make a Miller Act Payment Bond Claim?
A Miller Act payment bond claim, step by step: who can claim, the 90-day notice, the one-year suit deadline from 40 U.S.C. § 3133, with dated timeline.
· 8 min read
Money
Mechanic's Lien Deadlines: How They Work
How mechanic's lien deadlines are counted: the notices before, the filing deadline, the deadline to sue, and five states' filing deadlines from statute.
· 8 min read
Role hub
The Subcontractor's Guide: Bidding to Getting Paid
Every step of a commercial job from the subcontractor's seat: bidding, the subcontract, submittals, RFIs, change orders, pay apps, retainage and closeout.
· 9 min read