How Does California's 20-Day Preliminary Notice Work?

By Wyatt Cooper · Published · 8 min read

Key takeaways

  • On a California private job, a sub or supplier must give a preliminary notice to the owner, the direct contractor and any construction lender before it can record a lien, give a stop payment notice or claim on a payment bond (for a bond claim, § 8612's notice also counts).
  • The notice is due not later than 20 days after you first furnish work; a late notice still works, but only for work from 20 days before it was served onward.
  • The notice must carry the owner, contractor, lender and site details, a description of your work, an estimate of its total price and a boldface statement whose words the statute sets.
  • Serve it by personal delivery or by registered, certified, express or overnight mail, and keep the proof: notice by mail is given when it is deposited.

California's preliminary notice is the written notice a subcontractor or supplier gives the owner, the direct contractor and any construction lender to keep its lien, stop payment notice and payment bond rights. Civil Code § 8204 requires it not later than 20 days after you first furnish work. A late notice still counts, but only for work done in the 20 days before it was served and after. Laborers need not send one. Verify the current statute.

Who sends it and who gets it

A preliminary notice is the first step of California's lien process for private works, the "notice provided for in Chapter 2 (commencing with Section 8200)" (Civ. Code § 8034). Section 8200 says "before recording a lien claim, giving a stop payment notice, or asserting a claim against a payment bond, a claimant shall give preliminary notice" to the owner or reputed owner, the direct contractor the claimant works under, and the construction lender, if any (Civ. Code § 8200). Compliance "is a necessary prerequisite to the validity of a lien claim or stop payment notice." For the lien itself, see what a mechanic's lien is.

Who gives a California preliminary notice, and to whom (Civil Code §§ 8200 and 8206, read October 22, 2026)
Your place on the jobMust you give one?To whom
Direct contractor (contract with the owner)Only to the lenderThe construction lender or reputed lender, if any (§ 8200(e)(2))
Subcontractor of the direct contractorYesOwner, direct contractor, construction lender
Sub-subcontractor or supplier to a subYesOwner, direct contractor, construction lender
Supplier working under two different subs on one jobYes, one for each contractEach notice to the same three (§ 8206(b))
Laborer (an employee)No (§ 8200(e)(1))None

The 20-day rule, and what a late notice still covers

"A preliminary notice shall be given not later than 20 days after the claimant has first furnished work on the work of improvement" (Civ. Code § 8204). "Work" means "labor, service, equipment, or material provided to a work of improvement" (§ 8048), so the clock starts with your first delivery or your first day on site, whichever comes first.

Missing the 20 days does not end your rights. The same section says a claimant who did not give notice is not precluded from giving it later, but can record a lien, give a stop payment notice and claim on a bond "only for work performed within 20 days prior to the service of the preliminary notice, and at any time thereafter." Work before that window is unprotected. A design professional who gives notice within 20 days after the work of improvement has commenced is covered for its design services.

If the 20th day lands on a Saturday, Sunday or holiday, Code of Civil Procedure § 12a extends a period "provided or required by law" to the next day that is not a holiday, and it counts all of Saturday as a holiday (CCP § 12a). Don't plan around it: mail the notice the day you start.

What the notice must say

Section 8202 requires the notice to meet the general rules for notices in § 8102 and add three things (Civ. Code § 8202; § 8102):

  • From § 8102, to the extent known: the owner's or reputed owner's name and address; the direct contractor's; the construction lender's, if any; a description of the site, including its street address; your name, address and relationship to the parties; a general statement of your work; the name of the person you work for; and a statement or estimate of your demand.
  • "A general description of the work to be provided."
  • "An estimate of the total price of the work provided and to be provided."
  • The statement the statute prints in boldface, which begins "NOTICE TO PROPERTY OWNER EVEN THOUGH YOU HAVE PAID YOUR CONTRACTOR IN FULL" and explains that an unpaid claimant may place a lien on the property. Copy it word for word from § 8202(a)(3).

A notice "is not invalid by reason of any variance" if it substantially informs the person given notice (§ 8102(b)). The direct contractor "shall make available to any person seeking to give preliminary notice" the owner's and lender's names and addresses (§ 8208), so ask the GC for them when you sign. One notice covers all your work for that job, including work outside its description, unless you work under more than one subcontract there (§ 8206).

How to serve it and prove it

Notice must be in writing (§ 8100) and given by personal delivery, by mail as § 8110 provides, or by leaving it and mailing a copy as the Code of Civil Procedure allows for a summons (§ 8106). Mail means "registered or certified mail, express mail, or overnight delivery by an express service carrier" (§ 8110). Notice by mail is "complete and deemed to have been given" when deposited in the mail or with the carrier (§ 8116).

Keep the proof together for each job. Section 8118 requires a proof of notice declaration stating the notice given, the date, place and manner, and who received it, with the postal or carrier receipt or tracking record attached (§ 8118). You may also file the notice with the county recorder, which then mails filers a notice when a notice of completion or cessation is recorded on the property (§ 8214); that filing is optional and gives no notice to anyone else.

For a licensed subcontractor whose contract pays more than $400, failing to give the notice "constitutes grounds for disciplinary action" under the Contractors' State License Law (§ 8216). On home improvement jobs, the contract's required Mechanics Lien Warning tells the homeowner to expect these notices and to pay with joint checks (Bus. & Prof. Code § 7159(e)(4)).

Worked example: an on-time notice and a late one

A fictional tile subcontractor first delivers material to a fictional private remodel on Monday, March 2, 2026. Day one of the count is the day after (CCP § 12 excludes the first day), so the 20th day is Sunday, March 22.

Preliminary notice — first furnished Monday, March 2, 2026

20 days after first furnishing
Sunday, March 22, 2026
If § 12a's weekend rule is applied
Monday, March 23, 2026
Safe practice
Mail certified on March 2, the first day of work
If instead mailed late, on Wednesday, April 15, 2026
Covers only work from March 26, 2026 onward (20 days before service)
Work from March 2 through March 25 under the late notice
No lien, stop payment notice or bond claim for it
California preliminary notice dates for a sub that first furnished work on March 2, 2026 (fictional; verify before relying on it)

The count: March 2 plus 20 days is March 22. From April 15, 20 days back is March 26 (15 days back to March 31, five more). After the notice, the lien deadline itself is counted from completion of the whole project; see mechanic's lien deadlines.

The bottom line

Send California's preliminary notice the day you first deliver or start, by certified or overnight mail, with the statute's boldface wording and a fair estimate of your price, and keep the receipt with a proof of notice declaration. A late notice protects only work from 20 days before it.

Retention on the same private job has its own deadlines: see California retainage law. When you are paid, sign the right waiver (conditional vs unconditional), and for the rest of getting paid, see the subcontractor's guide.

Join the waitlist

Sources

  1. California Civil Code § 8034 — California Legislative Information. Read October 22, 2026.
  2. California Civil Code § 8102 — California Legislative Information. Read October 22, 2026.
  3. California Civil Code §§ 8106, 8110, 8116 and 8118 (giving notice) — California Legislative Information. Read October 22, 2026.
  4. California Civil Code § 8200 — California Legislative Information. Read October 22, 2026.
  5. California Civil Code § 8202 — California Legislative Information. Read October 22, 2026.
  6. California Civil Code § 8204 — California Legislative Information. Read October 22, 2026.
  7. California Civil Code §§ 8206, 8208, 8214 and 8216 — California Legislative Information. Read October 22, 2026.
  8. California Code of Civil Procedure §§ 12 and 12a — California Legislative Information. Read October 22, 2026.
  9. California Business and Professions Code § 7159 — California Legislative Information. Read October 22, 2026.
  10. Legislative information bulk download (pubinfo), the codes' official text — California Legislature. Read October 22, 2026.

Questions

Who has to send a preliminary notice in California?

On a private job, every subcontractor, sub-subcontractor and supplier who wants lien, stop payment notice or payment bond rights. A direct contractor with a contract with the owner sends one only to the construction lender, and an employee laborer sends none.

What happens if I send a California preliminary notice late?

It still works, but only for work you performed within 20 days before you served it and after. Anything you furnished earlier is outside your lien, stop payment notice and bond rights.

Does a preliminary notice have to be sent by certified mail?

It can be personally delivered, or mailed by registered or certified mail, express mail or overnight delivery by an express carrier. Mailed notice is given when deposited. Keep the receipt or tracking record with a proof of notice declaration.

Is a preliminary notice a lien?

No. It tells the owner, contractor and lender that you are working on the property and may claim a lien if unpaid. The lien is a separate claim recorded later, within deadlines counted from completion of the work of improvement.

Do I send a new notice when my scope grows?

Not for the same subcontract: a notice that describes your work generally also covers later work, even outside the description. You do need a separate notice for each subcontract if you work under more than one on the job.