What Is an O&M Manual?

By Wyatt Cooper · Published · 3 min read

Key takeaways

  • An O&M (operation and maintenance) manual is the owner's reference for running and maintaining each system after turnover.
  • Each trade supplies its part: manufacturer data, maintenance schedules, wiring and control diagrams, parts lists, warranties and contacts, organized by spec section.
  • It is a closeout submittal, reviewed like any other, and it is often a condition of final payment.

An O&M manual (operation and maintenance manual) is the set of documents a contractor hands the owner at closeout explaining how to run, maintain and repair the building's equipment and systems: manufacturer data, maintenance schedules, wiring and control diagrams, spare parts, warranties and supplier contacts. Each subcontractor supplies its part by specification section, and it is reviewed before turnover.

What goes in an O&M manual

The federal guide specification defines O&M data (submittal type SD-10) as data from the manufacturer or system provider "necessary to maintain and install equipment, for operating and maintenance use by facility personnel" and "Data required by operating and maintenance personnel for the safe and efficient operation, maintenance and repair of the item" (UFGS 01 33 00).

Its O&M section lays out the manual itself. For each system it asks for manufacturer's O&M data, approved submittals and shop drawings, the sequence of operation, startup and shutdown procedures, a preventive maintenance plan and schedule, troubleshooting guides, wiring and control diagrams, warranty and extended-warranty information, and a contractor and supplier contact list, followed by parts on facility operations, training and permits (UFGS 01 78 23). A private job's spec is usually shorter, but asks for the same core.

Example

Tab 23 74 00: rooftop units RTU-1 to RTU-3

Manufacturer data
Installation, operation and maintenance manual for the three units
Approved submittals
Product data, Rev 1, approved as noted
Sequence of operation
From the approved controls submittal
Maintenance schedule
Filters quarterly; belts and coils twice a year
Parts list
Filter sizes, belt numbers, fuse sizes
Warranty
1 year parts and labor from startup; 5 years on compressors
Contacts
Mechanical sub service line; manufacturer's local rep
One system's tab in an O&M manual (fictional equipment)

Collecting these tabs from every trade is the slow part of closeout; how to assemble a closeout package has the checklist, and what an owner gets at closeout is the owner's side.

O&M manual vs. as-builts vs. warranties

Three closeout documents that are easy to mix up
DocumentWhat it tells the owner
O&M manualHow to operate and maintain each system
As-built drawingsWhere everything actually is
Warranty lettersWho fixes what, for how long, from when

See as-built drawings and the warranty period.

How it works in Conflo

In Conflo's closeout package, O&M manuals are one of the deliverables, with as-builts, warranties, attic stock, training and lien waivers. The GC requests a whole spec section at once from the company that owes it, with one due date; items are grouped by spec section like the binder, approved or sent back with a note, and the package is delivered to the owner with the date and who delivered it on record.

The Closeout package in Conflo: closeout documents grouped by spec section and company, each requested, to review or approved with its file and due date, and progress toward delivering the package to the owner.
The closeout package in Conflo: documents grouped by spec section and company, each requested, to review or approved.

The bottom line

An O&M manual is the owner's instructions for the building, one tab per system.

Request it from each trade early, by spec section, and review it before turnover rather than after the first breakdown.

See how closeout works in Conflo

Sources

  1. UFGS 01 78 23, Operation and Maintenance Data (May 2023) — Whole Building Design Guide (USACE / NAVFAC / AFCEC). Read October 22, 2026.
  2. UFGS 01 33 00, Submittal Procedures (August 2026) — Whole Building Design Guide (USACE / NAVFAC / AFCEC). Read October 22, 2026.

Questions

Who prepares the O&M manual?

Each subcontractor and supplier provides the data for its systems; the general contractor collects, organizes and delivers the manual to the owner.

When is the O&M manual due?

The specification sets it, usually before substantial completion or owner training, and often in draft earlier for review.

Is an O&M manual paper or digital?

Either, as the specification says. Many owners now ask for searchable PDFs organized by spec section, sometimes with a printed copy too.