Owner update
Week of October 12, 2026
Riverside Medical Office · Prepared by Cobalt Builders for Northfield Health
- Schedule
- 3 days behind
- Substantial completion
- Contract
- $18.63M
- $64,200 in pending changes
- Your decisions
- 2 waiting
- Change order and pay app
This week
- Sheathing and air barrier complete on the north and east elevations.
- Roofing crew mobilized; membrane is down on 40% of the main roof.
- MEP rough-in continuing on Level 2; above-ceiling inspection set for Oct 22.
- Two days lost to rain on Oct 13–14.
Next three weeks
- Storefront installation starts Oct 26, once the shop drawings are approved.
- Roof membrane complete — dry-in remains on track for Nov 20.
- Level 1 framing and in-wall inspections.
Needs your decision
Schedule note
Substantial completion moves from Jun 9 to Jun 12, 2027 after the rain days. Roofing will work Saturdays through Nov 7 to protect dry-in.