How Does an Architect Write a Field Report?
By Wyatt Cooper · Published · 7 min read
Key takeaways
- An architect's field report records one site visit: what was observed, where, what doesn't conform to the contract documents, and what the architect is asking for.
- Write "observed", not "inspected" or "approved": a periodic visit doesn't check every part of the work, and the report shouldn't suggest it did.
- Tie each nonconforming item to the sheet or spec section it departs from, and say what you want: correction, an RFI, a submittal or a test.
- Number the items and carry the open ones to the next report until they close, so the owner and contractor can see what is still outstanding.
To write an architect's field report, record the visit's date, time, weather and who was present, the areas you observed and the work under way. List each item that departs from the contract documents with its location and the sheet or spec section, and what you are asking the contractor to do. Carry open items from the last report, attach dated photos, and send it to the owner and contractor promptly.
What a field report is for
During construction the architect visits the site to become generally familiar with the progress and quality of the work and to report what it finds to the owner. The AIA's summary of G711–2018, Architect's Field Report, describes the form as a record of periodic or daily site visits, used to record progress and quality observations, deviations from the contract documents and the schedule, and defects and deficiencies observed. AIA's owner-architect agreement sets the limit that shapes every report: the architect is not required to make exhaustive or continuous on-site inspections to check the quality or quantity of the work.
That limit is why the words matter. A field report that says the architect "inspected the framing and found it acceptable" claims more than a two-hour visit can support, and it can be read later as an approval. The rest of the architect's job during construction is in the architect's guide to construction administration.
What goes in the report
| Part | What to write | Avoid |
|---|---|---|
| Header | Project, report number, date, time on site, weather, who visited | A report with no number or time |
| Present | The contractor's and owner's people you met | Leaving out who you spoke to |
| Work in progress | Trades and areas working that day, in a line each | A narrative of the whole job |
| Areas observed | Where you went, and where you didn't | Implying you saw the whole building |
| Observations | Numbered items that depart from the documents, each with location and the sheet or spec section | "Looks good", "approved", "inspected" |
| Requested action | Correct, submit an RFI, provide a submittal, test, or uncover for observation | Directing means and methods |
| Open items | Earlier items by number, closed or still open | Starting fresh each visit |
| Photos and distribution | Dated photos keyed to item numbers; sent to the owner and contractor | Photos with no captions |
Keep "requested action" inside your role. Asking for work to be corrected to meet the documents is the architect's call; telling the contractor how to sequence or build it is not. A change to the design goes out as an architect's supplemental instruction or a change, not as a field report note.
A filled-in field report
Field Report 09 — Alder Street Medical Office — April 16, 9:30 to 11:45 AM
- Visited by
- Project architect, Fern Studio
- Weather
- Clear, 58°F
- Present
- GC superintendent; owner's representative (part of the visit)
- Work in progress
- Level 2 framing (east), level 1 electrical rough-in, storefront layout on the west elevation
- Areas observed
- Level 1, all; level 2 east and corridor. Not observed: level 2 west, roof
- 9.1 Corridor rated wall, level 2
- Observed gypsum board installed on one side before the head-of-wall joint is complete; detail 5/A-501 requires the joint system per the listed assembly. Requested: the contractor confirm the joint will be installed per the listing before the second side is closed.
- 9.2 Door 212 header
- Observed header smaller than shown on A-601. RFI 024 is open on this item. Requested: hold framing at door 212 until RFI 024 is answered.
- 9.3 Storefront sill, west elevation
- Observed sill flashing not yet installed; the reviewed shop drawings show a sill pan. Requested: notify the architect when the sill pan is in, before the frames are set.
- Open from report 08
- 8.2 Missing fire blocking at the corridor soffit: observed installed. Closed. 8.4 Roof drain locations: not observed this visit (roof not visited). Open.
- Photos
- 6 photos, keyed to items 9.1 to 9.3
- Distribution
- Owner's representative; GC project manager and superintendent; structural engineer (item 9.2)
Read the verbs: "observed", "requested", "not observed this visit". Item 8.4 stays open because the architect didn't go to the roof, not because it was checked and found wanting. And item 9.2 points to the open RFI instead of answering a design question in the field.
After the visit
- 1ArchitectVisits, observes and photographs, numbering each item on site
- 2ArchitectWrites and sends the report to the owner and contractor within a day or two
- 3General contractorCorrects, answers or submits what each item asks for
- 4ArchitectObserves the items at the next visit and marks them closed or open
Follow-up is where reports fail. Connecticut's construction administration manual has the construction administrator who runs state jobs "promptly prepare a written report" of work found unsatisfactory, faulty or defective, and follow up "to be certain the issue isn't simply reported on and the need for resolution overlooked". The same discipline works for an architect: an item stays on every report until it is closed.
When an owner's inspector rejects work, the procedure is more formal. On Los Angeles public works, a Notice of Non-Compliance can hold payment for the work in question; a field report is lighter, and it records what the architect observed and asked for.
Common mistakes
- "Inspected" and "approved". Write what you observed, and leave approval to the documents that give it.
- Not saying where you didn't go. A silence about the roof can read as no problems on the roof.
- Items without a reference. "Flashing incomplete" means more with the sheet and spec section next to it.
- Answering design questions in the report. Send them through the RFI, so the answer reaches everyone who builds from it.
- Sending it a week later. A report that arrives after the wall is closed can't change the wall.
The bottom line
A good field report says what the architect observed, where, and what it is asking for, tied to the sheet or spec section, in words that don't claim an inspection the visit didn't make. Number every item and carry it until it closes.
Conflo puts the design team on the same job as the GC and the owner, with RFIs and submittals answered in one place. Join the waitlist to try it.
Sources
- Summary: G711–2018, Architect's Field Report — AIA Contract Documents. Read October 22, 2026.
- 0600 Construction Administration Procedures Manual, §2.4 (inspection and reporting of deficient work) — State of Connecticut Department of Administrative Services. Read October 22, 2026.
- Project Delivery Manual, 17.6 Notices of Non-Compliance and Work Stoppage — City of Los Angeles, Bureau of Engineering. Read October 22, 2026.
Questions
What is an architect's field report?
A written record of one site visit by the architect during construction: the date, who was there, the areas observed, work in progress, items that depart from the contract documents, what the architect is asking for, and open items from earlier visits. AIA's form for it is G711.
Is an architect's site visit an inspection?
Not in the sense of checking every part of the work. AIA's owner-architect agreement says the architect is not required to make exhaustive or continuous on-site inspections; the visit is to become generally familiar with progress and quality, so write "observed", not "inspected".
Who gets the architect's field report?
The owner and the contractor, and any engineer or consultant whose work an item concerns. Send it within a day or two of the visit, so corrections can be made before work is covered.
What is the difference between a field report and a daily log?
The contractor's daily log records every day on site: weather, crews, work, deliveries, delays. The architect's field report records a periodic visit and what the architect observed and requested. Both are records; they answer to different parties.
Related
Role hub
The Architect's Guide to Construction Administration
The construction administration phase from the architect's seat: site visits, RFIs, ASIs, submittals, pay certification, changes and closeout.
· 8 min read
Construction
How Should an Architect Respond to an RFI?
How the design team answers an RFI: check it against the documents, answer the question asked, cite the sheet and spec, and say if it changes the work.
· 8 min read
Construction
How Does an Architect Write an ASI?
How an architect writes an ASI: what it may change, the parts of a good one, a filled-in example, and when it must become a change order.
· 8 min read
Construction
How Do Architects and Engineers Review a Submittal?
How the design team reviews a submittal: what the review covers and what it doesn't, choosing the review code, writing comments, and returning it on time.
· 8 min read