How Do You Issue a Subcontract Change Order?

By Wyatt Cooper · Published · 8 min read

Key takeaways

  • A subcontract change order is the signed document that changes one subcontract's price, time or scope; the owner's change order does not change the subcontract by itself.
  • Issue it once the owner's change is signed (or once you direct the work), at the sub's accepted cost, never at the owner's price with your markup.
  • Show the arithmetic on its face: original subcontract sum, earlier change orders, this change, and the new subcontract sum.
  • In the worked example, change order 3 for $6,214.08 takes a $412,600.00 subcontract to $426,064.08 after an earlier add and an earlier deduct.

To issue a subcontract change order, write a numbered change to that one subcontract: the subcontract and change numbers, the cause and the owner change order or directive it follows, the scope in plain words, the agreed amount at the sub's accepted cost, the days added, and the new subcontract sum after every earlier change. Both parties sign it, the GC updates the commitment and budget, and the sub bills it as its own line.

Two documents, two contracts

On a typical commercial job there are two contracts in a chain: the prime contract between the owner and the GC, and each subcontract between the GC and a sub. A change order signed by the owner changes the prime contract. It does not change the subcontract; only a change to the subcontract, signed by the GC and the sub, does that. Until it is issued, the sub has nothing to bill against and you have no record of what you agreed.

AIA publishes a contractor–subcontractor change order form (G701S). Its summary says that executing it indicates agreement on all the terms of the change, including any change in the contract sum (or guaranteed maximum price) and the contract time. Whatever form you use, it should do the same: one signed page that settles price, time and scope for that change.

  1. 1SubcontractorSends a priced change order request with backup
  2. 2GCReviews it and agrees the sub's cost
  3. 3OwnerSigns the prime contract change order at the GC's price
  4. 4GCIssues the subcontract change order at the sub's accepted cost
  5. 5SubcontractorSigns it and bills it on the next pay application
How a change reaches the subcontract on a typical commercial job.

When to issue one

  • After the owner signs a change that includes the sub's work: issue the matching subcontract change order at the cost you accepted in your review of the sub's request.
  • When you direct a change yourself, for example to move scope from one sub to another, or to add work the owner will not pay for: the subcontract still has to change, even with no owner change order behind it.
  • For a deduct, when work is deleted from the sub's scope: issue a negative change order so the subcontract sum, and the sub's billing, come down.
  • When only time changes: issue a no-cost change order that adds the days, so the schedule and the subcontract agree.

If you direct the sub to proceed before the price is agreed, say so in writing and say how it will be priced. Your prime contract likely works the same way: the federal changes clause lets the Contracting Officer make changes within the general scope by a written order, and treats other written or oral orders that cause a change as change orders only if the contractor gives written notice (FAR 52.243-4, paragraphs (a) and (b)). Give your sub the same clarity you need from the owner.

What goes on a subcontract change order

The parts of a subcontract change order and why each is there
PartWhat to writeWhy
NumbersThe subcontract number and the next change order number on itThe sub's billing and your commitment log reconcile by number
CauseThe owner change order, directive, RFI or bulletin it follows, by number and dateTies the sub's change to the prime contract change
ScopeWhat is added, deleted or changed, referencing the requestSettles what the price covers
AmountThe sub's accepted cost, including its allowed markupNever the owner's price with your markup
Revised sumOriginal sum, earlier changes, this change, new subcontract sumShows the arithmetic both sides agree
TimeDays added or saved, or "no change"A signed change with no time stated often settles time too
ReservationAny claim either side keeps open, stated in an amountOtherwise the signed change may be read as settling everything
SignaturesSomeone with authority at the GC and at the subIt is not a change until both sign

A worked example: change order 3 on a fictional electrical subcontract

The job and companies are fictional. A GC, "Corbel Construction", holds subcontract SC-014 with "Brightline Electric" for $412,600.00 on the "Halvorsen Office Fit-Out". Change order 1 added $8,450.00 for floor boxes. Change order 2 deducted $1,200.00 when the owner deleted two exterior sconces. The owner has now signed its change order 9, which includes the copy room circuits the GC accepted from Brightline at $6,214.08 and one working day.

Subcontract SC-014 before and after change order 3 (fictional; to the cent)
ItemAmountRunning subcontract sum
Original subcontract sum$412,600.00$412,600.00
Change order 1: floor boxes (add)$8,450.00$421,050.00
Change order 2: exterior sconces deleted (deduct)−$1,200.00$419,850.00
Change order 3: copy room circuits (add)$6,214.08$426,064.08
Net change by change orders$13,464.08

The check: $8,450.00 − $1,200.00 + $6,214.08 = $13,464.08, and $412,600.00 + $13,464.08 = $426,064.08. The owner's change order 9 carries the GC's 5% on top ($6,524.78 in all); the subcontract change carries only Brightline's accepted cost.

Subcontract SC-014, change order 3 — Copy room circuits

Project
Halvorsen Office Fit-Out (fictional)
Subcontractor
Brightline Electric (fictional)
Cause
Owner change order 9; architect's bulletin 6; Brightline request 011
Scope
Furnish and install eight dedicated 20 A circuits to the copy room, per bulletin 6 and request 011 as accepted by the GC
Amount
$6,214.08, including 15% overhead and profit
Subcontract sum
$412,600.00 original; $7,250.00 by change orders 1 and 2; $6,214.08 this change; $426,064.08 new sum
Time
1 working day added to the copy room activities
Reservation
None
Signatures
Corbel Construction project manager; Brightline Electric president
The subcontract change order as the GC issues it, on the fictional job. Every name, number and date is made up.

After it is signed

  • Update the commitment: the revised subcontract sum, the change order log and the balance left to bill.
  • Move the cost in the budget, by cost code, so committed cost and the budget agree.
  • Tell the sub how to bill it. Some owner specifications ask for each change order as a new line on the schedule of values; the University of Houston's payment procedures section, for example, says to include each change order as a new line item (Section 01 29 00).
  • Reconcile your change order log with the sub's every month, so pending and executed changes never get mixed on a pay application.

How the sub bills the change, including deducts and partly finished changes, is in how to bill a change order on a pay app. Where it sits among the GC's other jobs is in the general contractor's guide and the project lifecycle.

How it works in Conflo

In Conflo the GC can name the subcontractor on a change order it writes, and a change order a sub writes carries its company. When the owner approves it, the change order is executed and its page says the subcontract change order was issued to that sub, for the sub's cost. The cost also goes into the budget's approved changes by cost code.

On the sub's commitment, the change order is listed as approved (or pending while it is still in review), and the commitment shows the original value, approved change orders, the revised value, what has been billed and the balance. Limits today: every change order in Conflo goes to the owner for approval, so a change between the GC and a sub alone (a deduct or scope moved between subs with no owner change) is not issued in Conflo, and there is no separate signed subcontract change order document; if your subcontract needs one, sign it outside Conflo.

The Commitments list in Conflo: subcontracts and purchase orders with company and scope, payment holds, status, original and revised value, approved change orders, billed to date with percent, and retainage held.
Commitments in Conflo: each subcontract's original and revised value, approved change orders, billed to date and retainage held.

The bottom line

Issue a subcontract change order for every change to a sub's price, time or scope, at the sub's accepted cost, with the revised subcontract sum on its face and both signatures.

Then update the commitment and the budget the same day, so the sub's next pay application and your cost report agree.

See how commitments work in Conflo

Sources

  1. Summary: G701S–2017, Change Order, Contractor-Subcontractor Version — AIA Contract Documents. Read October 22, 2026.
  2. FAR 52.243-4, Changes — Acquisition.gov, U.S. General Services Administration. Read October 22, 2026.
  3. Section 01 29 00, Payment Procedures (master construction specification) — University of Houston, Facilities Planning and Construction. Read October 22, 2026.

Questions

What is a subcontract change order?

A signed change to one subcontract's price, time or scope, between the GC and that subcontractor. It follows the owner's change order, or a change the GC directs itself, and it is what the sub bills against.

Should a subcontract change order show the GC's markup?

No. It carries the sub's accepted cost, including the markup the subcontract allows the sub. The GC's own markup belongs on the owner's change order.

Can a GC issue a change order to a sub without an owner change order?

Yes, when the GC directs the change itself, such as moving scope between subs, adding work the owner will not pay for, or deleting work from the sub's scope. The subcontract's changes article says how.

How do you write a deduct change order?

Like an add, with a negative amount: the scope deleted, the credit, and the new, lower subcontract sum. The sub then shows it as a negative line on its schedule of values.

Does a signed change order settle the schedule too?

Often, if it states the time or says no change. If either side is keeping a time or cost claim open, write it on the change order in a stated amount before signing.