What Is an Invitation to Bid in Construction?
By Wyatt Cooper · Published · 4 min read
Key takeaways
- An invitation to bid (ITB) asks contractors for a firm price on work the documents already define, by a stated date and time.
- Federal rules call it an invitation for bids, and the responses to it are bids; a request for proposals gets proposals, and a request for quotations gets quotations.
- A general contractor sends one ITB per trade package, so each subcontractor prices only its own scope.
An invitation to bid (ITB) is the request an owner or general contractor sends to contractors asking for a price on defined work by a set deadline. It names the project and the scope, lists the drawings, specifications and addenda to price, and gives the due date, any bond and insurance requirements, and the bid form to return.
What an invitation to bid contains
An ITB carries everything a bidder needs to price the same work as every other bidder. Federal sealed bidding puts it plainly: invitations "must describe the requirements of the Government clearly, accurately, and completely," and the invitation "includes all documents (whether attached or incorporated by reference) furnished prospective bidders for the purpose of bidding" (FAR 14.101). On private work, the owner's instructions to bidders do the same job; AIA publishes one as A701, Instructions to Bidders (AIA).
Invitation to bid: electrical
- Project
- Larkspur Clinic, tenant improvement
- Package
- 26 Electrical
- Documents
- Drawings E0.1–E4.2; spec Divisions 26 and 28; Addendum 1
- Scope
- Written scope with 14 numbered items
- Alternates
- Alt 1: LED fixture upgrade in corridors
- Questions due
- March 3, 2:00 p.m.
- Bids due
- March 10, 2:00 p.m.
- Requirements
- Bid on the attached form; insurance per the subcontract; 100% performance and payment bond as a separate add
How to write and send one, step by step, is in how to send an invitation to bid. The package it goes out with is a bid package, and its heart is the scope of work.
Invitation to bid vs. RFP vs. RFQ
| Request | What comes back | How the award is decided |
|---|---|---|
| Invitation to bid (invitation for bids) | Bids | Price, on documents already complete |
| Request for proposals (RFP) | Proposals | Price and other factors, often with negotiation |
| Request for quotations (RFQ) | Quotations, which are not offers | Usually small purchases |
In FAR 2.101, "solicitations under sealed bid procedures are called 'invitations for bids,'" and the responses are offers called bids. On private jobs the words blur, but the difference holds: an ITB asks for a price on defined work; an RFP asks how a contractor would do the work and for how much.
How it works in Conflo
In Conflo's trade bids, each package has its scope, scope items, alternates and a due date and time. You invite subcontractors from your directory, see each invitation move from invited to viewed, bidding, declined or submitted, and answer questions once for every bidder.

The bottom line
An invitation to bid is a request for a firm price on defined work, with everything the bidder needs attached and a deadline to meet.
Send one per trade, with the same documents to every bidder, and the bids that come back can be compared.
Sources
- FAR 2.101, Definitions (solicitation, offer) — Acquisition.gov, U.S. General Services Administration. Read October 22, 2026.
- FAR 14.101, Elements of sealed bidding — Acquisition.gov, U.S. General Services Administration. Read October 22, 2026.
- List of document synopses by family (A701, Instructions to Bidders) — AIA Contract Documents. Read October 22, 2026.
Questions
Is an invitation to bid the same as an invitation for bids?
Yes. Federal and many public agencies say invitation for bids (IFB); contractors often say invitation to bid (ITB) or bid invite. All mean a request for sealed or firm prices on defined work.
Does an invitation to bid bind the GC to award?
Usually not. A private invitation normally reserves the right to reject any bid. Public sealed bidding is stricter: the award goes to the responsible bidder whose conforming bid is most advantageous on price.
What should a subcontractor check in an ITB first?
The due date and time, the documents and addenda listed, the scope items, and any bond and insurance requirements. Price exactly what is listed, and ask before the questions deadline about anything unclear.
Related
Bidding
How Do You Send an Invitation to Bid to Subs?
What an invitation to bid to subs includes, how to send it, and how to run questions and addenda so every bid prices the same scope, with an example.
· 7 min read
Definition
What Is a Bid Package in Construction?
A bid package is the scope and documents sent out for one price, usually one trade's work. What goes in it, an example, and bid package vs. bid set.
· 3 min read
Definition
What Is a Scope of Work in Construction?
A scope of work says what a contractor will and won't do, and which documents it rests on. Definition, an example, and scope vs. specifications.
· 3 min read
Role hub
The General Contractor's Guide: Bid to Closeout
What a general contractor is responsible for at every phase of a commercial job, from bidding and buyout to RFIs, change orders, pay apps and closeout.
· 8 min read