How to Write Construction Meeting Minutes (With Example)
By Wyatt Cooper · Published · 7 min read
Key takeaways
- Construction meeting minutes record what was decided and who owes what by when, not a transcript of who said what.
- Number every item by the meeting it was first raised in, so item 11.3 is still 11.3 three meetings later and its age is obvious.
- Every open item needs one responsible party and a date; an item without both isn't an action item.
- Send the minutes within a day, ask for corrections by a stated deadline, and accept them at the start of the next meeting.
To write construction meeting minutes, start with the project, meeting number, date, place and who attended. Then record old business and new business as numbered items, each with what was discussed, what was decided, who is responsible and the due date. Mark items closed or carried, attach the current logs and look-ahead, and send the minutes within a day with a deadline for corrections.
What minutes are for
Minutes are the job's record of decisions and promises. The City of Los Angeles Bureau of Engineering's minutes procedure says they are prepared "to provide a record of items discussed and decisions made" and to "track and follow-up on the tasks and responsibilities assigned at the meetings", and that they should "report the facts of the meeting without bias".
That last part matters because minutes get read later by people who weren't there: a new project manager, the owner's lender, a scheduler working out a delay. Connecticut's construction administration manual lists meeting minutes among the records used to assess a claim. Write them as if someone will.
This post is about the record. For running the meeting itself, see how to run an OAC meeting.
The parts of a good set of minutes
| Part | What to write | Common mistake |
|---|---|---|
| Header | Project, meeting type and number, date, time, place, who wrote them | No meeting number, so nobody can cite them |
| Attendance | Each person, company and role, marked present or absent | Listing the invitees as if they all came |
| Review of last minutes | Corrections received and that the minutes were accepted | Silently editing last week's minutes |
| Old business | Each carried item by its original number, with status: closed, or still open with a new date | Dropping items nobody mentioned |
| New business | New items numbered from this meeting (14.1, 14.2), each with the decision, owner and date | Paragraphs of discussion and no decision |
| Attachments | The look-ahead and the current RFI, submittal and change order logs | "See logs" with nothing attached |
| Next meeting and corrections | The next date, and a deadline for corrections | No correction window, so disputes surface months later |
Los Angeles asks for each of these. Its minutes include a statement that corrections are due "within 5 calendar days of receipt of minutes", and the weekly meeting's minutes carry the contractor's three-week schedule and the updated submittal, RFI and change order logs as attachments. Connecticut asks for "an action list detailing items requiring follow-up, the parties responsible, the schedule by when action is expected".
A filled-in example: minutes of OAC meeting #14
Here are the minutes from the agenda in the OAC meeting post, on the same made-up job. Notice that every line ends with a name and a date, or with "Closed".
Minutes — OAC Meeting #14 — Alder Street Medical Office — April 7, 10:00 AM, site trailer
- Present
- Owner's rep (Alder Health); project architect (Fern Studio); MEP engineer, for item 14.1; GC project manager (writer) and superintendent
- Absent
- Structural engineer (no items this week)
- Minutes of #13
- No corrections received. Accepted.
- 11.3 IT room equipment list (old)
- Owner has the list from its IT vendor; sends it April 9. Owner's rep, due April 9. Open.
- 13.2 Door hardware schedule (old)
- Issued April 6 as ASI 004. Closed.
- 14.1 RFI 019 roof drain sizing (new)
- MEP engineer will answer by April 9; roof drains are on the path to the April 20 roof deck. MEP engineer, due April 9.
- 14.2 Storefront shop drawings (new)
- Architect will return reviewed drawings by April 14 to hold the 6-week lead time. Architect, due April 14.
- 14.3 PCO 007 added floor drains, $4,860 (new)
- Owner approves; GC to issue the change order for signature. GC PM, due April 9.
- 14.4 Card readers at two doors (new)
- Owner asked for a price. GC PM, due April 14.
- Attachments
- Three-week look-ahead dated April 6; RFI, submittal and change order logs as of April 6
- Next meeting
- April 14, 10:00 AM, site trailer
- Corrections
- Send corrections to the GC PM within 5 calendar days of receipt; otherwise these minutes stand.
Item 14.3 shows the most common gap. The owner said yes in the room, but a verbal approval doesn't change the contract. The minutes record it and give the GC a date to put the change order in front of the owner for signature.
From the meeting to the next agenda
- 1GC project managerWrites the minutes from the notes the same day
- 2GC project managerSends them to every attendee and anyone given an item
- 3AttendeesSend corrections in writing before the deadline
- 4GC project managerRevises and redistributes if anything changed
- 5Next meetingAccepts the minutes; open items become old business
Federal quality control specs follow the same loop. UFGS 01 45 00 has the contractor's QC manager prepare minutes of the coordination meeting, signed by the contractor, the architect-engineer and the government, with a copy to every attendee. Each weekly quality control meeting then starts by reviewing the minutes of the previous one.
Common mistakes
- Writing who said what. Record the decision and the next step; leave the argument out.
- Vague owners: "design team", "all". Name the company, and the person if you can.
- Editing sent minutes. Correct them through the next set, so everyone has the same version.
- Recording a cost or time decision and stopping there. It still needs a written change; how to write a change order request shows the sub's side.
- Minutes nobody receives. The Los Angeles meetings procedure distributes the minutes to all attendees; include anyone given an item, even if they weren't in the room.
How it works in Conflo
In Conflo's meetings tool, the GC takes attendance and writes the minutes on the meeting itself, and adds each action item with an assignee from the project team and a due date. The meeting is then marked complete. Meetings past their time with no minutes are flagged on the list.
You pick who gets the minutes from the whole project team, including people who weren't invited. Once the minutes are marked distributed they lock, and other parties can read them. Open action items carry to the next meeting in the series with a link back to where they started, and the minutes download as a PDF with attendance and every action item's status.
The bottom line
Good minutes are short: a header, attendance, numbered items each ending in a name and a date or "Closed", the logs attached, and a deadline for corrections. Keep each item's number from the meeting it started in.
If carrying open items forward by hand is where your minutes break down, let the meeting series carry them.
Sources
- Project Delivery Manual, 16.7 Meeting Minutes — City of Los Angeles, Bureau of Engineering. Read October 22, 2026.
- Project Delivery Manual, 16.6 Meetings — City of Los Angeles, Bureau of Engineering. Read October 22, 2026.
- 0600 Construction Administration Procedures Manual, §2.4.5 Project Meetings — State of Connecticut Department of Administrative Services. Read October 22, 2026.
- UFGS 01 45 00, Quality Control (August 2023, change 4) — Naval Facilities Engineering Systems Command (Whole Building Design Guide). Read October 22, 2026.
Questions
What should construction meeting minutes include?
The project, meeting number, date, place and attendance; acceptance of the last minutes; old and new business as numbered items, each with the decision, responsible party and due date; the current logs and look-ahead as attachments; the next meeting date; and a deadline for corrections.
Who writes the minutes at a construction meeting?
Whoever runs the meeting, usually the general contractor's project manager or, on some public jobs, the owner's construction manager. The contract's Division 01 project meetings section may say who records and distributes them.
How soon should meeting minutes be sent?
Within a day, while everyone still agrees on what was said. Give a deadline for corrections; the City of Los Angeles uses five calendar days from receipt.
How do you number items in meeting minutes?
By the meeting the item was first raised in, then a sequence: 14.1, 14.2 for new items at meeting 14. A carried item keeps its number until it closes, so 11.3 at meeting 14 has been open for three meetings.
Can meeting minutes be changed after they are sent?
Corrections go in writing to the author and are accepted at the next meeting, which amends the record. Don't silently edit a set already sent; everyone should hold the same version.
Related
Construction
How Do You Run an OAC Meeting?
How a GC runs an owner-architect-contractor meeting: who attends, what each party brings, a worked agenda, and how open items carry to the next one.
· 8 min read
Construction
How to Write a Construction Daily Log (With Example)
How to write a construction daily log: what to record each day, a filled-in example, and the habits that make a log hold up in a delay claim.
· 6 min read
Role hub
The General Contractor's Guide: Bid to Closeout
What a general contractor is responsible for at every phase of a commercial job, from bidding and buyout to RFIs, change orders, pay apps and closeout.
· 8 min read
Construction
How Does an Architect Write an ASI?
How an architect writes an ASI: what it may change, the parts of a good one, a filled-in example, and when it must become a change order.
· 8 min read