How Should an Owner Review a Change Order?

By Wyatt Cooper · Published · 8 min read

Key takeaways

  • Review a change order in four passes: is it really a change, is the direct cost right, are the markups the ones the contract allows, and are the days real.
  • GSA's cost policy has its estimator price a change before the contractor's proposal comes in, to the same level of detail, and review each cost for accuracy, reasonableness and allowability.
  • Ask for the credit for deleted work: a change that swaps one item for another should be priced as the new work minus the old.
  • In the worked example, the owner's review takes a $17,125.80 change order to $11,549.66 by applying the contract's 5% markup and the credit for deleted fixtures.

To review a change order as an owner, check four things in order. First, that it is a change: the work is not already in the contract documents, and the cause is documented. Second, the direct cost: quantities, rates and quotes you can check, with credits for deleted work. Third, the markups: only the percentages the contract allows, applied once. Fourth, the days: a schedule fragment showing the critical path moves. Then approve, or reject with reasons.

Is it really a change?

Start with the contract documents, not the price. A change order is owed only for work that differs from what the contract required. Ask the architect, or whoever wrote the drawings, whether the work was shown or specified. Then read the cause the contractor gives: an owner request, a design error or omission, a concealed condition, or an RFI answer that changed the design.

Check two more things before pricing. Is the work covered by an allowance already in the contract? Then it is an allowance adjustment, not new money. And did the contractor give notice on time? Federal contracts, for example, allow no adjustment for costs incurred more than 20 days before written notice of a constructive change (FAR 52.243-4); private contracts set their own periods.

Check the direct cost line by line

The best check is your own number. The U.S. General Services Administration's cost policy (P120) has its estimator prepare an independent estimate before a change request goes to the contractor, at the same level of detail as the contractor's proposal, and review the proposal's costs for accuracy, reasonableness and allowability. Most private owners will not go that far on every change, but the method scales: have your architect, cost consultant or owner's representative price the large ones.

  • Labor: hours that fit the scope, at rates backed by payroll records, not a round percentage.
  • Materials: supplier quotes or invoices, with tax and delivery where they apply.
  • Subcontractor work: each sub's own quote, with its breakdown.
  • Credits: when work is swapped, the net is the new work minus the deleted work. P120 has its estimator compute the net cost or credit the same way, and counts decreases and increases at their full value when deciding whether a change needs an independent estimate.

Hold the markups to the contract

Your contract's changes article usually states the markups: overhead and profit on the contractor's own work, a lower rate on subcontracted work, and sometimes insurance and bond at cost. Check each percentage against the contract, and check what it is applied to. The two common errors are a self-performed rate applied to a subcontractor's quote, and markup added on top of a sub's quote that already contains the sub's own markup at a rate the contract does not allow.

If your contract is silent on markups, the rate is negotiated, and a published public rate is a reasonable reference. To see how a markup changes the total, try the change order pricing calculator; the contractor's side of the same math is in how to price a change order.

Ask for the schedule logic behind the days

Days cost you money too: extended general conditions, later occupancy, and, if the days are left open, a delay claim later. Ask for the schedule fragment: the activities the change touches, whether they are on the critical path, and the new dates. P120 asks for schedule-related and impact costs to be shown as a separate part of each estimate; ask the contractor to do the same, so you can see what you are paying for time.

If a change has no effect on the critical path, it should carry no days. If it does, approving the days in the same change order as the money settles the question for that change.

A worked example: a fixture swap on a fictional renovation

The job is fictional: "Harbor Point Library Renovation". The owner asks for 18 reading-room light fixtures to be a different model. The GC's change order carries the electrical sub's quote of $14,600.00, a 15% GC markup, 2% for insurance and bond, and 6 days. The fictional contract allows 5% on subcontracted work and insurance and bond at 2%.

The change order as submitted and after the owner's review (fictional; to the cent)
LineAs submittedAfter reviewWhat the owner checked
Electrical sub's quote$14,600.00$10,784.00Credit for the 18 original fixtures not bought: 18 × $212.00 = $3,816.00
GC markup on sub work$2,190.00 (15%)$539.20 (5%)The contract allows 5% on subcontracted work
Subtotal$16,790.00$11,323.20
Insurance and bond, 2%$335.80$226.462% × $11,323.20 = $226.464
Change order total$17,125.80$11,549.66$5,576.14 less
Time6 days0 daysThe schedule fragment shows the fixtures arrive before ceilings close

Every figure is rounded to the cent where shown: $14,600.00 − $3,816.00 = $10,784.00; 5% of that is $539.20; and $17,125.80 − $11,549.66 = $5,576.14.

Change order 012 — Reading-room fixture change: owner review

Project
Harbor Point Library Renovation (fictional)
Decision
Returned for revision
Scope
Agreed: owner request, not in the contract documents
Credit
Show the credit for the 18 base-bid fixtures not purchased ($212.00 each per the sub's submittal pricing)
Markup
Contract section on changes: 5% on subcontracted work, not 15%
Time
Send the schedule fragment; we see no effect on ceiling close-in
Next step
We will approve at $11,549.66 and 0 days on receipt of the revised change order
The owner's review notes sent back to the GC, on the fictional job. Every name, number and date is made up.

Approve, reject, or send it back

The owner's change order review checklist
CheckAsk forCommon finding
Is it a change?The cause, its document, and the architect's viewWork already shown or specified
Direct costQuotes, crew hours, rates, invoicesHours or a lump sum with nothing behind them
CreditsThe cost of any deleted workAn add-only price for a swap
MarkupsThe contract's percentages and what each applies toOwn-work rate on a sub's quote
TimeA schedule fragment with the critical pathDays for work with float
Running totalApproved and pending changes against your contingencyPending changes larger than what is left

Keep a running total of approved and pending change orders against the contingency you set aside. Once a change is executed it raises the contract sum, and the contractor bills it on the next pay application, where retainage is usually held on it too.

How it works in Conflo

In Conflo the owner sees a change order once the GC sends it for approval: the scope, the reason and the RFI it came from, the schedule days, each line at the owner's price, and the decision due date. The GC's cost codes, cost lines and markup are not shown to the owner, and neither is the cost backup; the Files section is shared with everyone on the change order.

A Contract impact panel shows the original contract, the change orders already approved, this one, what the contract becomes if it is approved and the percent change against the original, and the other change orders still pending. The owner approves in one step, which executes the change order, or rejects it with a reason the GC sees. Limits today: there is no place for the owner's own estimate of the change, and no field for a requested credit; put those in the rejection reason or a file.

A change order as the owner sees it in Conflo, waiting on their approval: the price, two days added to the schedule, what the contract becomes and when the decision is due, Reject and Approve buttons, the scope description, line items at the owner's price with no cost codes or markup, the GC review step already done, and the RFI that caused the change.
A change order waiting on the owner in Conflo: the price, the days, what the contract becomes, and the lines at the owner's price.

The bottom line

An owner's review is four questions in order: is it a change, is the cost right, are the markups the contract's, and are the days real. Ask for the credit when work is swapped, and price the big ones yourself before the contractor's number arrives.

Send back what you cannot check with the reason in writing, and approve the money and the days together.

See how change orders work in Conflo

Sources

  1. P120, Public Buildings Service Cost and Schedule Management Policy Requirements (GSA Order PBS 1000.6B, November 7, 2022) — U.S. General Services Administration, via the Whole Building Design Guide. Read October 16, 2026.
  2. FAR 52.243-4, Changes — Acquisition.gov, U.S. General Services Administration. Read October 16, 2026.

Questions

How does an owner check a change order price?

Compare it with your own estimate of the change, or your architect's or cost consultant's, at the same level of detail. Check quantities, labor hours and rates, quotes and invoices, any credit for deleted work, and that each markup is the contract's rate on the right base.

What markup should an owner accept on a change order?

The markup the contract states. Many contracts allow one rate on the contractor's own work and a lower rate on subcontracted work, with insurance and bond at cost. If the contract is silent, the rate is negotiated. Check your contract.

Can an owner reject a change order?

An owner can reject or return a change order request it disagrees with, in writing and with reasons. If the contract lets the owner direct the work before the price is agreed, the owner may issue a change directive instead and settle the price later.

Should an owner approve schedule days on a change order?

Approve days the schedule supports. Ask for a fragment showing the change moves the critical path. If it does, settle the days in the same change order as the money; if the work has float, it should carry no days.