How Does a No-Damages-for-Delay Clause Work?
By Wyatt Cooper · Published · 7 min read
Key takeaways
- A no-damages-for-delay clause gives you more time when the job is delayed but no money for the cost of the delay, even when someone else caused it.
- Read whose delays it covers: a clause that covers delays caused by the GC or owner is the one that costs subs the most.
- Some states limit these clauses; Washington, for one, makes void any construction-contract clause waiving damages for unreasonable delay caused by the party you contract with.
- Before signing, ask for carve-outs, a cap in days after which delay is paid, and notice terms you can meet, and price what is left as a risk.
A no-damages-for-delay clause says that if your work is delayed, your only remedy is an extension of time: no payment for the extra cost of being on the job longer, such as supervision, equipment, and labor and material escalation. Many clauses apply even when the GC or owner caused the delay. Some states limit them by statute. Before you sign, read whose delays it covers, ask for exceptions or a day cap, and price the remaining risk.
What the clause does
A delay costs a sub in two ways: time, because the work finishes later, and money, because the crew, the foreman, the trailer and the rented lift stay on the job longer, and labor and material can cost more by the time you get to them. A no-damages-for-delay clause separates the two. It grants the time, usually as an extension of the subcontract schedule, and takes away the money.
| Clause | Time | Money for the delay | What to watch |
|---|---|---|---|
| No clause; contract silent | An extension, as the changes or delay clause provides | Recoverable, with proof and notice | Notice deadlines in the general terms |
| Broad no-damages-for-delay | An extension only | None, whoever caused it | Words like "for any cause whatsoever" |
| No damages except for the GC's or owner's own acts | An extension | Recoverable when the GC or owner caused it | How "caused by" is proven |
| No damages for the first set number of days | An extension | Recoverable after the stated number of days | Whether the days are per event or for the whole job |
| Pass-through only | An extension | Only what the GC recovers from the owner for you | That the GC must actually pursue your claim |
Where the law limits it: one state and federal work
Washington is an example of a state that limits these clauses by statute. RCW 4.24.360 says a clause in a construction contract "which purports to waive, release, or extinguish the rights of a contractor, subcontractor, or supplier to damages or an equitable adjustment arising out of unreasonable delay in performance which delay is caused by the acts or omissions of the contractee or persons acting for the contractee is against public policy and is void and unenforceable." It does not void provisions that require notice of delays, provide for arbitration or another settlement procedure, or "provide for reasonable liquidated damages." RCW 4.24.370 defines the construction contracts it covers.
Read the qualifiers: the delay must be unreasonable, and caused by the party you contract with (for a sub, usually the GC) or people acting for it. A notice clause still applies, so a late notice can lose a claim the statute would otherwise protect. Other states have their own rules or none; this page names only the one read for it.
Federal prime contracts take a different route. The Suspension of Work clause, FAR 52.242-14, says that if work is suspended, delayed or interrupted "for an unreasonable period of time" by an act of the contracting officer, or by the contracting officer's failure to act in time, "an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit)". It bars costs incurred more than 20 days before the contractor notified the contracting officer in writing, except for a claim from a suspension order. That clause is between the government and the prime; your subcontract decides how much of it reaches you.
A worked example: what the clause costs
Delay on the Oak Hollow School job: slab release 15 working days late
- Cause
- The GC released the second-floor slab 15 working days late
- Extended supervision
- $1,200 a day × 15 days = $18,000
- Equipment held on site
- $350 a day × 15 days = $5,250
- Total delay cost
- $18,000 + $5,250 = $23,250, or $1,550 a day
- Broad no-damages-for-delay clause
- 15 working days added to the schedule; $0
- Clause with a 10-day threshold
- 15 − 10 = 5 days × $1,550 = $7,750
- Clause excepting the GC's own delays
- $23,250, if notice was given on time
Check it: $1,200 + $350 = $1,550 a day, and $1,550 × 15 = $23,250. The difference between the broad clause and the GC exception is the whole $23,250, on one event. A job with three such delays turns the clause into a five-figure risk you either negotiate or price.
What to ask before you sign
- Whose delays does it cover? Ask that delays caused by the GC, the owner or the design team be excepted.
- Is there a number of days after which delay is paid? A threshold is a common middle ground.
- What notice does it require, how many days after the delay starts, and to whom? Put that deadline on your calendar the day you sign.
- Does it also bar acceleration costs, if the GC asks you to make up the lost time?
- Does it flow down from the prime contract? Ask to see the owner's version; you can rarely get better terms than the GC has.
- If the clause stays, price it: add a contingency, shorten your bid's validity, or qualify your proposal.
For writing up the proposal with those qualifications, see how to write a subcontractor proposal. For the rest of the subcontract's terms, see how to buy out a construction job, and the subcontractor's guide for every step after.
The bottom line
A no-damages-for-delay clause trades your money for time: an extension, and nothing for the cost of being there longer. Read whose delays it covers, and treat a clause that covers the GC's own delays as a priced risk.
Ask for an exception for the GC's and owner's delays or a day threshold, meet every notice deadline, and have an attorney read the clause under the law of the state where the job is.
Sources
- RCW 4.24.360, Construction contract provision waiving rights to damages for unreasonable delay: void — Washington State Legislature. Read October 22, 2026.
- RCW 4.24.370, "Construction contract" defined — Washington State Legislature. Read October 22, 2026.
- FAR 52.242-14, Suspension of Work — Acquisition.gov. Read October 22, 2026.
Questions
What does no damages for delay mean in a subcontract?
That if your work is delayed, you get more time but no money for the delay's cost. Many versions apply even when the GC or owner caused it.
Are no-damages-for-delay clauses enforceable?
It depends on the state and the facts. Some states limit them by statute: Washington's RCW 4.24.360 voids clauses waiving damages for unreasonable delay caused by the party you contract with. Ask an attorney in the state where the job is.
What can a subcontractor negotiate instead?
An exception for delays the GC, owner or design team cause; a number of days after which delay is paid; and notice terms you can meet. If none is possible, price the risk into your bid.
Does a no-damages-for-delay clause stop a time extension?
Usually not: it typically grants the extension and bars the money. Read the clause, since some limit extensions too, and give notice on time either way.
How does federal work handle delay costs?
Under FAR 52.242-14, the government adjusts the prime contract for cost increases, excluding profit, from an unreasonable suspension or delay caused by the contracting officer. How much reaches a sub depends on the subcontract.
Related
Bidding
How to Write a Sub Proposal a GC Can Level
Write a subcontractor bid proposal the GC can level: match its scope items, break out prices, price exclusions, and see what the GC does with each line.
· 7 min read
Preconstruction
How Do You Buy Out a Construction Job?
Construction buyout step by step: scope review, leveling, award, the subcontract and its exhibits, compliance documents, and savings against budget.
· 7 min read
Preconstruction
How Does an Indemnity Clause in a Subcontract Work?
How a subcontract's indemnity clause works: broad, intermediate and limited forms, a worked claim under each, one state's limits, and what to ask.
· 7 min read
Bidding
How Do You Bid a GC's Job as a Subcontractor?
How a subcontractor bids commercial work for a GC: choosing jobs, reading the invitation, pricing, writing a bid the GC can level, and what comes after.
· 7 min read
Role hub
The Subcontractor's Guide: Bidding to Getting Paid
Every step of a commercial job from the subcontractor's seat: bidding, the subcontract, submittals, RFIs, change orders, pay apps, retainage and closeout.
· 9 min read