How Should an Owner Write an RFP for a GC?
By Wyatt Cooper · Published · 7 min read
Key takeaways
- An RFP is the document general contractors answer, so it should ask for exactly what you will score, in the order you will score it.
- State the evaluation factors and their relative weight in the RFP itself; contractors write better proposals when they know what counts.
- Ask for the price in a fixed form (fee percent, general conditions, insurance and bond rates) so a low fee cannot hide a high total.
- Give a full schedule: the questions deadline, addenda, proposal due date, interviews and award, and one contact for everything.
An owner's RFP for a general contractor should describe the project, the delivery method and the contract form, ask for exactly what you will score (experience, team, approach and schedule, safety, and a fee in a set format), state the evaluation factors and their relative weight, and give the schedule: questions deadline, proposal due date, interviews and award. Ask every firm for the same items in the same order, so the proposals compare side by side.
The RFP is the document the contractors answer
Choosing a general contractor starts with deciding what you need and who to ask; how an owner chooses a GC covers that. This piece is about the document you send the shortlisted firms. A vague RFP gets proposals that cannot be compared: one firm sends a brochure, another a fee with no general conditions, a third a schedule with no assumptions, and you spend the evaluation leveling proposals instead of judging them.
Federal source selection is a good model even for a private owner. "All factors and significant subfactors that will affect contract award and their relative importance shall be stated clearly in the solicitation", and the solicitation says whether all factors other than cost, combined, are significantly more important than, about equal to, or significantly less important than cost (FAR 15.304). Federal RFPs also split the instructions (Section L: how to prepare the proposal) from the evaluation (Section M: the factors and their relative importance) (FAR 15.204-5). Keep both in yours.
The sections of a GC RFP
| Section | What to include |
|---|---|
| 1. Project | Location, program, size, budget range, design status and the drawings and reports attached |
| 2. Delivery method and contract | Lump sum, construction manager at risk with a guaranteed maximum price, or design-build; the contract form to be used, attached |
| 3. Services | Preconstruction services wanted (estimates at each design stage, constructability review, schedule) and construction services |
| 4. Schedule | Design milestones, the expected start, substantial completion and any phasing or occupied-building limits |
| 5. Proposal instructions | What to submit, in what order, page limits, format, and how and where to deliver it |
| 6. Price form | Fee percent, general conditions by month, insurance and bond rates, self-performed labor rates; a form to fill in, not a free-form letter |
| 7. Evaluation | The factors, their weights or relative importance, and whether interviews are scored |
| 8. Requirements | Bonding, insurance limits, licensing, prevailing wage or participation goals if they apply |
| 9. Questions and addenda | One contact, the last day for questions, and that answers go to all firms by addendum |
| 10. Terms | Proposal validity period, the owner's right to reject all proposals, confidentiality, and no contact with others on the owner's team |
Choose the delivery method before you write, because it changes what you ask for. A lump-sum bid needs complete documents and a price; a guaranteed maximum price contract signed early needs a fee, general conditions and a preconstruction approach. The delivery methods compared page sets the options side by side.
A worked example: a fee form that compares
Harlow Clinics (fictional) is hiring a construction manager at risk for a clinic with an estimated cost of the work of $12,000,000. Its price form asks every firm for the same four numbers. To keep the example simple, the fee and the insurance and bond rate are both applied to the $12,000,000 cost of the work; a real RFP should say exactly what each rate is applied to.
| Firm | Fee | General conditions | Insurance and bonds | Total for comparison | Price points (of 25) |
|---|---|---|---|---|---|
| Ashby Construction | 4.0% = $480,000 | $68,000 × 14 months = $952,000 | 1.6% = $192,000 | $1,624,000 | 23.3 |
| Brennan Builders | 3.5% = $420,000 | $74,000 × 14 months = $1,036,000 | 1.8% = $216,000 | $1,672,000 | 22.6 |
| Calder & Rhee | 4.5% = $540,000 | $61,000 × 13 months = $793,000 | 1.5% = $180,000 | $1,513,000 | 25.0 |
Brennan's fee is the lowest, but its total is the highest, because its general conditions cost more per month. Calder & Rhee has the highest fee and the lowest total, partly because it proposes 13 months instead of 14: a claim to test at the interview, since a month saved only counts if the schedule is credible. Price points follow the formula stated in the RFP: the lowest total gets the full 25 points, and each other firm gets 25 × lowest total ÷ its total. Ashby: 25 × $1,513,000 ÷ $1,624,000 = 23.3. Brennan: 25 × $1,513,000 ÷ $1,672,000 = 22.6.
The other 75 points in this RFP are experience (25), the proposed team (20), approach and schedule (20) and safety (10), each stated in the evaluation section with what earns full marks. Because the weights were published, every firm knew price was a quarter of the decision and wrote accordingly.
Run the process in a fixed order
- 1OwnerIssues the RFP to the shortlisted firms, with the schedule and one contact
- 2ContractorsAsk questions in writing by the deadline
- 3OwnerAnswers every firm at once by numbered addendum
- 4ContractorsSubmit proposals in the required order and price form
- 5Owner's panelScores the written proposals against the stated factors, then interviews
- 6OwnerNegotiates with the top-ranked firm and awards
Some owners split the process in two. Federal two-phase design-build is one example: phase one evaluates technical approach and technical qualifications, such as specialized experience, capability to perform and the team's past performance, and expressly excludes cost or price factors; price comes in phase two from the short list (FAR 36.303-1). A private owner can do the same: qualifications first, then a full RFP with the fee form to three firms.
Mistakes that weaken an RFP
- Asking for "your fee" with no form, then comparing a percentage against a lump sum.
- Hiding the weights, then scoring mostly on price.
- No page limit, so the longest proposal looks the most thorough.
- Changing the scope in a phone call with one firm instead of an addendum to all.
- Leaving the contract form out of the RFP, so exceptions surface after selection.
- Interviewing without a scoring sheet written in advance.
Once a firm is selected, it runs its own bidding to the trades; the owner's guide follows the job from there to closeout.
The bottom line
A good RFP for a general contractor tells the firms what you will score and how much each part counts, asks for the price in one form, and fixes the schedule and the rules before the first question arrives.
Write it that way and the proposals arrive comparable, the interviews test real differences, and the award is one you can explain to your board.
Sources
- FAR 15.304, Evaluation factors and significant subfactors — Acquisition.gov, U.S. General Services Administration. Read October 22, 2026.
- FAR 15.204-5, Part IV, Representations and Instructions (Sections L and M) — Acquisition.gov, U.S. General Services Administration. Read October 22, 2026.
- FAR 36.303-1, Phase One (two-phase design-build) — Acquisition.gov, U.S. General Services Administration. Read October 22, 2026.
Questions
What should an RFP for a general contractor include?
The project description, delivery method and contract form, the services wanted, the schedule, proposal instructions, a price form, the evaluation factors and their weights, requirements such as bonding and insurance, the questions and addenda process, and the terms of the RFP itself.
What is the difference between an RFP and an invitation to bid?
An invitation to bid asks for a price on complete documents and is usually awarded to the lowest responsible bidder. A request for proposals asks for price and other information, such as team, approach and schedule, and is scored on several factors.
Should an owner tell GCs how proposals will be scored?
Yes. Stating the factors and their relative weight lets each firm put its effort where it counts, and it makes the decision easier to defend. Federal rules require it in negotiated procurements.
How do you compare general contractor fees?
Ask every firm for the same numbers in a price form, such as fee percent, general conditions per month, months, and insurance and bond rates, then compare the totals on the same cost of work. A low fee can sit beside high general conditions.
Related
Bidding
How Should an Owner Choose a General Contractor?
How a commercial owner chooses a general contractor: pick the delivery method, shortlist on qualifications, check bonding and references, then price.
· 7 min read
Bidding
How Should an Owner Compare Contractor Proposals?
How an owner compares general contractor proposals: put them on one sheet, price every exclusion and allowance, check schedule and terms, then decide.
· 6 min read
Definition
Design-Bid-Build vs Design-Build vs CM at Risk
Design-bid-build, design-build and CM at risk compared for owners: who holds which contract, when the price is fixed, and when each one fits.
· 4 min read
Definition
What Is a GMP Contract in Construction?
A GMP contract caps what the owner pays: the cost of the work plus a fee, up to a ceiling. A worked example of shared savings and an overrun.
· 4 min read
Role hub
The Owner's Guide to a Commercial Building Project
The owner's role on a commercial building project, phase by phase: delivery method, choosing the contractor, pay apps, change orders and closeout.
· 7 min read