How Do You Estimate a Bathroom Remodel?
By Wyatt Cooper · Published · 7 min read
Key takeaways
- A bathroom estimate is mostly hidden work: price demolition, the subfloor, the plumbing rough-in and the shower's waterproofing before the finishes the client sees.
- Take off tile by the square foot for each surface, add waste, and round up to full boxes; carry the tile itself as an allowance until the client picks it.
- Add a contingency for what's behind the walls and under the toilet, then markup; the example's 25% markup is a 20% margin.
- Write the scope as specifically as the price, with every allowance and exclusion named, because the estimate becomes the contract.
To estimate a bathroom remodel, measure the room and every tiled surface, write the scope line by line, and price each line from your crew's hours, your material takeoff and your subs' written quotes. Price the hidden work first: demolition, subfloor repair, plumbing rough-in, venting and waterproofing. Carry fixtures and tile the client hasn't chosen as allowances. Then add permits, supervision, a contingency for what's behind the walls, and your markup.
Measure the room and the wet areas
Walk the bathroom with the client and write down what a kitchen walk doesn't need: the floor and every wall surface that gets tile, in square feet; the shower or tub's size and whether it is a tub, a pan or a curbless floor; where the toilet, drain and valve sit and whether they move; how the fan vents; whether the floor is soft at the toilet or tub; and the outlets near water. Moving a drain or a toilet is a plumbing line of its own, and a soft floor is a subfloor line.
Note the year the house was built. Under the EPA's Renovation, Repair and Painting rules, firms doing work that disturbs lead-based paint in homes built before 1978 "must be EPA- or state-certified and must use certified renovators who follow specific work practices." Price that work, or the testing that shows it isn't needed.
| Item | Measure | Price it from |
|---|---|---|
| Floor tile | Floor area in sq ft, plus waste for cuts, rounded up to full boxes | Tile allowance per sq ft; setter's quote for labor |
| Shower walls | Each wall's width × tile height, in sq ft | Same as floor tile |
| Waterproofing and backer | Shower wall and pan area | Material from the takeoff; your crew's hours |
| Plumbing | Fixtures that stay, move or are added; valve type | Plumber's written quote, rough and finish |
| Electrical | Fan, lights, protected outlets, any new circuit | Electrician's written quote |
| Subfloor and framing | Soft areas, blocking for grab bars and vanity | Crew hours and material |
| Fixtures and vanity | Count and the client's level of finish | Allowances until chosen |
Price each line, hidden work first
Price your own crew as hours times a loaded labor rate (wage plus taxes, insurance and benefits). Price subbed trades from written quotes, and read the exclusions: a tile quote that leaves out the shower pan or the waterproofing membrane is not the tile price. The figures below are an example to replace with your own rates, quotes and allowances.
| Line | How it was priced | Cost |
|---|---|---|
| Demolition and haul-off | 12 hours × $60 loaded rate = $720, plus a $400 dumpster | $1,120 |
| Subfloor repair and blocking | 6 hours × $60 = $360, plus $240 material | $600 |
| Plumbing, rough and finish | Plumber's written quote: new valve, drain moved for the shower | $3,200 |
| Electrical | Electrician's quote: fan, light, protected outlet | $1,400 |
| Waterproofing and backer | $450 material plus 8 hours × $60 = $480 | $930 |
| Tile setting | Setter's quote, floor and shower walls | $3,600 |
| Tile, allowance | 125 sq ft (121 needed, rounded to full boxes) × $8 | $1,000 |
| Vanity, top and faucet, allowance | Client hasn't chosen | $1,800 |
| Toilet and shower trim, allowance | Client hasn't chosen | $700 |
| Glass shower door | Glazier's quote | $1,500 |
| Drywall repair and paint | Painter's quote | $1,100 |
| Accessories (mirror, bars, hooks) | 4 hours × $60 | $240 |
| Permit and fees | The building department's fee schedule | $350 |
| Supervision, protection and cleanup | Your own time, floor protection, final clean | $1,460 |
| Total cost | $19,000 |
The tile count: floor 5 × 8 = 40 sq ft; shower walls 70 sq ft (a 5-foot back wall and two 2.5-foot ends, 7 feet high: 35 + 17.5 + 17.5); 110 sq ft plus 10% waste is 121 sq ft, ordered as 125.
Contingency, markup and the price
Lin hall bath — estimate summary
- Total cost (the table above)
- $19,000
- Contingency, 8% of cost
- $19,000 × 8% = $1,520
- Cost with contingency
- $19,000 + $1,520 = $20,520
- Markup, 25% of $20,520
- $5,130
- Price to the client
- $20,520 + $5,130 = $25,650
- Gross margin
- $5,130 ÷ $25,650 = 20%
- Allowances inside the price
- $1,000 + $1,800 + $700 = $3,500 of cost
- Check
- The 14 cost lines add to $19,000; $25,650 − $20,520 = $5,130
Bathrooms earn a larger contingency than many rooms because the worst surprises sit under the toilet and behind the tub: rot at the flange, a joist cut for a drain, old supply lines. Set it from the house's age and what you saw at the walk. For why a 25% markup is a 20% margin, see markup vs margin; for the difference between the contingency and the allowances, see allowance vs contingency.
Turn it into a proposal
- Describe every line the way it will read in the contract. California's license board advises naming "the style, brand, model, quality, quantity, weight, color, size" of materials (CSLB, Terms of Agreement).
- List each allowance, what it covers (material, delivery, tax) and how the price changes if the pick is above or below it. Selections are their own job: see how to manage client selections.
- List exclusions plainly: moving a wall, rooms outside the bath, mold remediation beyond a set area.
- Tie payments to work done. In California the down payment may not exceed "one thousand dollars ($1,000) or 10 percent of the contract amount, whichever amount is less," so the Lin job could ask for $1,000 up front, not $2,565 (Bus. & Prof. Code § 7159.5). Check your state's rules.
- Say how changes are priced, in writing before the work: see how to handle a change order on a remodel.
The bottom line
A bathroom estimate is a measured takeoff of every tiled surface and fixture, priced line by line with the hidden work first, allowances for what the client hasn't chosen, a contingency for what's under the floor and a markup you have converted to margin.
Conflo is built for commercial construction today, and its residential tools are not built yet. Join the waitlist to hear when they are, and see the residential builder's guide for the rest of the job, or how to estimate a kitchen remodel for the room next door.
Sources
- Terms of Agreement: A Consumer Guide to Home Improvement Contracts — California Contractors State License Board. Read October 22, 2026.
- Lead Renovation, Repair and Painting Program Rules — U.S. Environmental Protection Agency. Read October 22, 2026.
- California Business and Professions Code § 7159.5 — California Legislative Information. Read October 22, 2026.
Questions
How do contractors estimate a bathroom remodel?
They measure the room and every tiled surface, write the scope line by line, price their own work as hours times a loaded rate plus material, price subbed trades from written quotes, carry unchosen fixtures and tile as allowances, then add permits, supervision, contingency and markup.
How much tile waste should I add?
Enough for cuts and breakage on that layout; the example uses 10%. Large tiles, diagonal patterns and small rooms with many cuts need more. Round up to full boxes, and keep a few spare tiles for the client.
What hidden costs show up in bathroom remodels?
Rot at the toilet flange or under the tub, a joist notched for an old drain, failed supply lines, a fan vented into the attic instead of outside, and paint that needs lead-safe work in a house built before 1978. Price what you can see and carry a contingency for the rest.
Should fixtures be allowances in a bathroom estimate?
If the client hasn't chosen them, yes. Write the amount and what it covers, such as purchase, delivery and tax, and say how the price changes if the client picks something above or below it.
What markup should a remodeler use on a bathroom?
One that covers your overhead and the profit you need, worked out as a margin. A 25% markup on cost is a 20% margin on price; if you need a 25% margin, the markup is 33.3%.
Related
Bidding
How Do You Estimate a Kitchen Remodel?
How a remodeler estimates a kitchen: line items by trade, allowances for the client's picks, contingency and markup, with a worked $63,000 example.
· 6 min read
Bidding
Markup vs Margin: How Should a Contractor Price Work?
Markup is a percentage of cost; margin is a percentage of price. A 20% markup is a 16.7% margin. Conversion table and a worked remodel example.
· 5 min read
Preconstruction
How Do Remodelers Manage Client Selections?
How remodelers manage client selections: one selections sheet, deadlines from lead times, allowances with rules, and a change order for every overage.
· 5 min read
Role hub
The Residential Builder's Guide: Estimate to Warranty
The residential construction process step by step for builders and remodelers: estimate, contract, selections, draws, walkthrough and warranty.
· 8 min read